2 min readThe control cycle
- Plan (baseline).
- Measure actual progress, cost and quality.
- Compare with the plan.
- Analyse variances and causes.
- Act: corrective actions or approved changes.
- Report and repeat (weekly or monthly).
Earned value management (EVM)
Combines scope, time and cost into one picture.
- PV (planned value): budgeted cost of the work scheduled to date.
- EV (earned value): budgeted cost of the work actually done to date.
- AC (actual cost): what the work done has actually cost.
- BAC: budget at completion.
Measures:
- Schedule variance SV = EV − PV; schedule performance index SPI = EV/PV.
- Cost variance CV = EV − AC; cost performance index CPI = EV/AC.
- Estimate at completion EAC = BAC/CPI (if the current cost performance continues); estimate to complete ETC = EAC − AC.
Values below 1 for SPI or CPI mean behind schedule or over budget.
Example
BAC = ₦100 million. At month 5: PV = ₦50 m, EV = ₦40 m, AC = ₦45 m.
- SV = 40 − 50 = −₦10 m (behind schedule); SPI = 0.80.
- CV = 40 − 45 = −₦5 m (over budget); CPI = 40/45 ≈ 0.889.
- EAC = 100/0.889 = ₦112.5 m; ETC = 112.5 − 45 = ₦67.5 m.
Check: EAC = AC + (BAC − EV)/CPI = 45 + 60/0.889 = 45 + 67.5 = 112.5 ✓.
Interpretation: only 80% of the planned work is done and each naira spent buys about 89 kobo of planned work; without action the project will overrun by about ₦12.5 m.
Measuring progress
Physical progress by milestones achieved, units installed (metres of pipe welded, cubic metres of concrete), weighted steps (for a valve: delivered 20%, installed 50%, tested 80%, handed over 100%). Avoid "percentage complete" guesses.
Crashing (shortening the schedule)
To finish earlier, spend more on critical activities (overtime, extra crews, faster equipment).
- Cost slope = (crash cost − normal cost) / (normal time − crash time).
- Crash the critical activity with the lowest cost slope first, one step at a time, watching for new critical paths.
Example
| Activity | Normal | Crash | Cost slope |
|---|---|---|---|
| P (critical) | 10 days, ₦50,000 | 6 days, ₦70,000 | 20,000/4 = ₦5,000/day |
| Q (critical) | 8 days, ₦40,000 | 6 days, ₦52,000 | 12,000/2 = ₦6,000/day |
To save 3 days, crash P first: 3 × 5,000 = ₦15,000 extra (if P stays critical and the indirect costs saved, such as site overheads of ₦8,000 a day, exceed this, crashing pays: 3 × 8,000 = ₦24,000 saved > ₦15,000).
Change control
All changes to scope, time or cost go through a change request: describe, assess impact, approve or reject, update the baseline. Uncontrolled changes ("scope creep") are a main cause of overruns.
Reports
Progress reports with S-curves (PV, EV, AC against time), a few key indicators, issues, risks and decisions needed. Keep them short and honest.
Exams usually ask
- Define PV, EV and AC and calculate SV, CV, SPI, CPI and EAC.
- Explain the project control cycle and change control.
- Use cost slopes to crash a project network.
Common mistake
Comparing actual cost with planned value to judge cost performance. Compare AC with EV (the value of the work actually done); PV measures schedule.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Earned value management
(opens en.wikipedia.org in a new tab)
Wikipedia, Earned value management, CC BY-SA 4.0 · licence
-
Project management triangle
(opens en.wikipedia.org in a new tab)
Wikipedia, Project management triangle, CC BY-SA 4.0 · licence
-
Program evaluation and review technique
(opens en.wikipedia.org in a new tab)
Wikipedia, Program evaluation and review technique, CC BY-SA 4.0 · licence
-
OpenStax, Principles of Management (whole free textbook)
The whole book, free to read online or download as a PDF (the PDF is large: Wi-Fi).
(opens openstax.org in a new tab)
OpenStax, OpenStax, Principles of Management (whole free textbook), CC BY-NC-SA 4.0 · licence
Watch
-
Best pick Problem 1 Crashing of Network - Project Monitoring and Cost Control - Construction Management
26 min · ≈ 117 MB · about ₦66
(opens youtube.com in a new tab)
-
What is Earned Value Management - EVM? PM in Under 5
6 min · ≈ 27 MB · about ₦15
(opens youtube.com in a new tab)
-
Monitoring And Control | Project Management Life Cycle | Invensis Learning
20 min · ≈ 90 MB · about ₦51
(opens youtube.com in a new tab)
-
Research & Development in the Project Control Earned Value Management
20 min · ≈ 90 MB · about ₦51
(opens youtube.com in a new tab)
-
Lecture - 16 Project Monitoring and Control with PERT/Cost
58 min · ≈ 261 MB · about ₦147
(opens youtube.com in a new tab)
We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.