Project control: monitoring, earned value and crashing

Comparing progress with the baseline, earned value analysis, forecasting completion cost, and crashing a schedule.

Our notes

2 min read

The control cycle

  1. Plan (baseline).
  2. Measure actual progress, cost and quality.
  3. Compare with the plan.
  4. Analyse variances and causes.
  5. Act: corrective actions or approved changes.
  6. Report and repeat (weekly or monthly).

Earned value management (EVM)

Combines scope, time and cost into one picture.

  • PV (planned value): budgeted cost of the work scheduled to date.
  • EV (earned value): budgeted cost of the work actually done to date.
  • AC (actual cost): what the work done has actually cost.
  • BAC: budget at completion.

Measures:

  • Schedule variance SV = EV − PV; schedule performance index SPI = EV/PV.
  • Cost variance CV = EV − AC; cost performance index CPI = EV/AC.
  • Estimate at completion EAC = BAC/CPI (if the current cost performance continues); estimate to complete ETC = EAC − AC.

Values below 1 for SPI or CPI mean behind schedule or over budget.

Example

BAC = ₦100 million. At month 5: PV = ₦50 m, EV = ₦40 m, AC = ₦45 m.

  • SV = 40 − 50 = −₦10 m (behind schedule); SPI = 0.80.
  • CV = 40 − 45 = −₦5 m (over budget); CPI = 40/45 ≈ 0.889.
  • EAC = 100/0.889 = ₦112.5 m; ETC = 112.5 − 45 = ₦67.5 m.

Check: EAC = AC + (BAC − EV)/CPI = 45 + 60/0.889 = 45 + 67.5 = 112.5 ✓.
Interpretation: only 80% of the planned work is done and each naira spent buys about 89 kobo of planned work; without action the project will overrun by about ₦12.5 m.

Measuring progress

Physical progress by milestones achieved, units installed (metres of pipe welded, cubic metres of concrete), weighted steps (for a valve: delivered 20%, installed 50%, tested 80%, handed over 100%). Avoid "percentage complete" guesses.

Crashing (shortening the schedule)

To finish earlier, spend more on critical activities (overtime, extra crews, faster equipment).

  • Cost slope = (crash cost − normal cost) / (normal time − crash time).
  • Crash the critical activity with the lowest cost slope first, one step at a time, watching for new critical paths.

Example

ActivityNormalCrashCost slope
P (critical)10 days, ₦50,0006 days, ₦70,00020,000/4 = ₦5,000/day
Q (critical)8 days, ₦40,0006 days, ₦52,00012,000/2 = ₦6,000/day

To save 3 days, crash P first: 3 × 5,000 = ₦15,000 extra (if P stays critical and the indirect costs saved, such as site overheads of ₦8,000 a day, exceed this, crashing pays: 3 × 8,000 = ₦24,000 saved > ₦15,000).

Change control

All changes to scope, time or cost go through a change request: describe, assess impact, approve or reject, update the baseline. Uncontrolled changes ("scope creep") are a main cause of overruns.

Reports

Progress reports with S-curves (PV, EV, AC against time), a few key indicators, issues, risks and decisions needed. Keep them short and honest.

Exams usually ask

  • Define PV, EV and AC and calculate SV, CV, SPI, CPI and EAC.
  • Explain the project control cycle and change control.
  • Use cost slopes to crash a project network.

Common mistake

Comparing actual cost with planned value to judge cost performance. Compare AC with EV (the value of the work actually done); PV measures schedule.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All ENG 502 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.