ENG 502 · Engineering Management
Our notes
2 min readCost engineering
Cost engineering applies engineering judgement and experience to cost estimating, cost control, planning and profitability analysis. Accurate estimates are essential for investment decisions, tenders and budgets.
Capital and operating costs
- Capital cost (CAPEX): the one-off cost of building or buying the facility: land, design, equipment, materials, construction, commissioning, start-up, working capital.
- Operating cost (OPEX): the yearly cost of running it (next topic).
Classes of estimate
Accuracy improves as design advances. A common five-class scheme (AACE International) gives roughly:
| Class | Stage | Typical accuracy range |
|---|---|---|
| 5 | concept screening | about −30% to +50% |
| 4 | feasibility study | about −20% to +30% |
| 3 | budget authorisation (FEED) | about −15% to +20% |
| 2 | control / bid | about −10% to +15% |
| 1 | check estimate / definitive | about −5% to +10% |
Capacity scaling: the six-tenths rule
Cost does not rise in proportion to capacity; larger plants are cheaper per unit (economies of scale):
C₂ = C₁ (Q₂/Q₁)^n, with n often about 0.6 for whole plants (0.4-0.8 for equipment).
Example: a plant of 10,000 t/yr cost US$20 million. A 25,000 t/yr plant: C₂ = 20 × (2.5)^0.6 ≈ 20 × 1.733 ≈ US$34.7 million: 2.5 times the capacity for about 1.7 times the cost.
Cost indices (time adjustment)
Prices change with time: C_now = C_then × (Index_now / Index_then). Examples of indices: the Chemical Engineering Plant Cost Index (CEPCI), Nelson-Farrar (refineries), national price indices.
Example: the US$20 million cost was for a year with index 550; the index now is 800: 20 × 800/550 ≈ US$29.1 million.
In Nigeria, exchange-rate changes matter as much as inflation: imported equipment costs in naira can rise sharply when the naira falls (as after the 2023 exchange-rate unification), so state the currency and date of every estimate.
Factored estimates
- Lang factor: total plant cost ≈ factor × delivered cost of the main equipment. Typical Lang factors: about 3.1 for solids processing, 3.6 for mixed solid-fluid, 4.7 for fluid processing plants.
Example: equipment for a fluid processing plant delivered at ₦2 billion: total ≈ 4.74 × 2 = ₦9.5 billion.
- Detailed factors (Hand, Guthrie): separate factors for installation, piping, instruments, electrical, buildings, engineering and contingency.
Detailed estimates
At later stages: quantity take-off from drawings (tonnes of steel, metres of pipe, cubic metres of concrete), unit rates (labour, materials, plant), vendor quotations, subcontract prices, indirect costs (site facilities, supervision, insurance), plus contingency and escalation.
Elements of a capital cost estimate
Direct costs (equipment, bulk materials, construction labour); indirect costs (engineering, project management, temporary facilities, freight and duties, insurance); owner's costs (land, permits, start-up, training); contingency; escalation (inflation during the project); working capital.
Exams usually ask
- Describe the classes of capital cost estimate and their accuracy.
- Use the six-tenths rule and cost indices.
- Make a factored estimate with the Lang factor.
Common mistake
Using the six-tenths rule over very large capacity ranges or for a different technology. It applies to similar plants within about a tenfold range of size.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Cost estimate
(opens en.wikipedia.org in a new tab)
Wikipedia, Cost estimate, CC BY-SA 4.0 · licence
-
Cost engineering
(opens en.wikipedia.org in a new tab)
Wikipedia, Cost engineering, CC BY-SA 4.0 · licence
-
Capital cost
(opens en.wikipedia.org in a new tab)
Wikipedia, Capital cost, CC BY-SA 4.0 · licence
-
OpenStax, Principles of Management (whole free textbook)
The whole book, free to read online or download as a PDF (the PDF is large: Wi-Fi).
(opens openstax.org in a new tab)
OpenStax, OpenStax, Principles of Management (whole free textbook), CC BY-NC-SA 4.0 · licence
Watch
-
Best pick How to Estimate Project Costs: A Method for Cost Estimation
12 min · ≈ 54 MB · about ₦30
(opens youtube.com in a new tab)
-
What is Cost Engineering?
7 min · ≈ 32 MB · about ₦18
(opens youtube.com in a new tab)
-
Lang Factor - Economic Evaluation of Chemical Process
6 min · ≈ 27 MB · about ₦15
(opens youtube.com in a new tab)
-
AACE Cost Estimate Classification System for Process Industries
14 min · ≈ 63 MB · about ₦35
(opens youtube.com in a new tab)
-
ENGR 221 - Class 3 (1/30/2014) Cost Estimation and Cost Index
42 min · ≈ 189 MB · about ₦106
(opens youtube.com in a new tab)
We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.