ENG 502 · Engineering Management

Cost engineering: capital cost estimating

Classes of estimate, the cost of a plant, scaling with the six-tenths rule, cost indices and factored estimates.

Our notes

2 min read

Cost engineering

Cost engineering applies engineering judgement and experience to cost estimating, cost control, planning and profitability analysis. Accurate estimates are essential for investment decisions, tenders and budgets.

Capital and operating costs

  • Capital cost (CAPEX): the one-off cost of building or buying the facility: land, design, equipment, materials, construction, commissioning, start-up, working capital.
  • Operating cost (OPEX): the yearly cost of running it (next topic).

Classes of estimate

Accuracy improves as design advances. A common five-class scheme (AACE International) gives roughly:

ClassStageTypical accuracy range
5concept screeningabout −30% to +50%
4feasibility studyabout −20% to +30%
3budget authorisation (FEED)about −15% to +20%
2control / bidabout −10% to +15%
1check estimate / definitiveabout −5% to +10%

Capacity scaling: the six-tenths rule

Cost does not rise in proportion to capacity; larger plants are cheaper per unit (economies of scale):

C₂ = C₁ (Q₂/Q₁)^n, with n often about 0.6 for whole plants (0.4-0.8 for equipment).

Example: a plant of 10,000 t/yr cost US$20 million. A 25,000 t/yr plant: C₂ = 20 × (2.5)^0.6 ≈ 20 × 1.733 ≈ US$34.7 million: 2.5 times the capacity for about 1.7 times the cost.

Cost indices (time adjustment)

Prices change with time: C_now = C_then × (Index_now / Index_then). Examples of indices: the Chemical Engineering Plant Cost Index (CEPCI), Nelson-Farrar (refineries), national price indices.
Example: the US$20 million cost was for a year with index 550; the index now is 800: 20 × 800/550 ≈ US$29.1 million.
In Nigeria, exchange-rate changes matter as much as inflation: imported equipment costs in naira can rise sharply when the naira falls (as after the 2023 exchange-rate unification), so state the currency and date of every estimate.

Factored estimates

  • Lang factor: total plant cost ≈ factor × delivered cost of the main equipment. Typical Lang factors: about 3.1 for solids processing, 3.6 for mixed solid-fluid, 4.7 for fluid processing plants.

  Example: equipment for a fluid processing plant delivered at ₦2 billion: total ≈ 4.74 × 2 = ₦9.5 billion.

  • Detailed factors (Hand, Guthrie): separate factors for installation, piping, instruments, electrical, buildings, engineering and contingency.

Detailed estimates

At later stages: quantity take-off from drawings (tonnes of steel, metres of pipe, cubic metres of concrete), unit rates (labour, materials, plant), vendor quotations, subcontract prices, indirect costs (site facilities, supervision, insurance), plus contingency and escalation.

Elements of a capital cost estimate

Direct costs (equipment, bulk materials, construction labour); indirect costs (engineering, project management, temporary facilities, freight and duties, insurance); owner's costs (land, permits, start-up, training); contingency; escalation (inflation during the project); working capital.

Exams usually ask

  • Describe the classes of capital cost estimate and their accuracy.
  • Use the six-tenths rule and cost indices.
  • Make a factored estimate with the Lang factor.

Common mistake

Using the six-tenths rule over very large capacity ranges or for a different technology. It applies to similar plants within about a tenfold range of size.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All ENG 502 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.