Operating costs, contingencies and allowances

Fixed and variable operating costs, unit cost and break-even, and how contingency, escalation and allowances are set.

Our notes

2 min read

Operating cost (OPEX)

The yearly cost of running a plant, site or system.

Variable costs (rise with output)

Raw materials, fuel and power, chemicals and catalysts, consumables, royalties per unit, packaging, transport.

Fixed costs (do not change with output in the short run)

Salaries of permanent staff, maintenance (partly), insurance, rent, property taxes, administration, depreciation (for accounting).

Semi-variable costs

Maintenance and some labour (overtime) have fixed and variable parts.

Unit cost and break-even

Total operating cost = F + vQ. Unit cost = F/Q + v.

Example

Fixed costs ₦50 million a year; variable cost ₦2,000 a unit; output 40,000 units:

  • Total = 50 m + 2,000 × 40,000 = 50 m + 80 m = ₦130 million.
  • Unit cost = 130 m/40,000 = ₦3,250.

If the selling price is ₦4,500 a unit, the break-even output is F/(p − v) = 50 m/2,500 = 20,000 units (check: revenue 20,000 × 4,500 = ₦90 m = 50 m + 2,000 × 20,000 ✓).
Running near full capacity spreads fixed costs and lowers unit cost; that is why capacity utilisation matters.

Oil and gas operating costs

Often expressed as cost per barrel of oil equivalent (US$/boe): lifting cost, transport, processing, security (a major cost in parts of the Niger Delta), host community obligations and regulatory levies under the Petroleum Industry Act 2021.

Contingency

Contingency is money added to an estimate for uncertain items within the scope that experience says will occur but cannot yet be identified: incomplete design detail, quantity growth, price uncertainty within the market, minor errors.

  • Typical contingency falls as the estimate class improves: perhaps 25-40% at concept stage, 10-15% at the budget stage and 5-10% for a definitive estimate (guides only).
  • It is not for changes of scope, major disasters or strikes (those are management reserve or insurance).
  • Better: set contingency by risk analysis: list risks with probabilities and cost impacts, or run a Monte Carlo simulation and choose, for example, the P80 value (an 80% chance of not being exceeded).

Example (expected-value method): risk A, 30% chance, ₦10 m; risk B, 10% chance, ₦40 m; risk C, 50% chance, ₦4 m. Expected cost = 3 + 4 + 2 = ₦9 million: a starting point for contingency.

Allowances

Allowances are amounts for known items whose quantity or cost is not yet fully defined: for example, an allowance for cable trays before the cable routing is designed, for small-bore piping, for wastage and offcuts (say 5% on steel bars), for weather downtime on site, or for import duties.
They are part of the base estimate, unlike contingency.

Escalation

An allowance for price rises over time between the estimate date and when the money is spent: (inflation rate) × (time to mid-point of spending). Example: ₦1 billion of work spent mainly in 2 years' time at 20% a year inflation: about 1 × (1.2² − 1) = ₦440 million of escalation if spent at the end of year 2; less if spread out. Use separate rates for imported (foreign currency) and local items.

Exams usually ask

  • Classify operating costs into fixed and variable and compute unit cost and break-even.
  • Distinguish contingency, allowances and escalation.
  • Explain how contingency can be estimated from risks.

Common mistake

Using contingency to pay for new work the client adds. That is a scope change and must be priced and approved separately.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All ENG 502 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.