ENG 502 · Engineering Management
Our notes
2 min readOperating cost (OPEX)
The yearly cost of running a plant, site or system.
Variable costs (rise with output)
Raw materials, fuel and power, chemicals and catalysts, consumables, royalties per unit, packaging, transport.
Fixed costs (do not change with output in the short run)
Salaries of permanent staff, maintenance (partly), insurance, rent, property taxes, administration, depreciation (for accounting).
Semi-variable costs
Maintenance and some labour (overtime) have fixed and variable parts.
Unit cost and break-even
Total operating cost = F + vQ. Unit cost = F/Q + v.
Example
Fixed costs ₦50 million a year; variable cost ₦2,000 a unit; output 40,000 units:
- Total = 50 m + 2,000 × 40,000 = 50 m + 80 m = ₦130 million.
- Unit cost = 130 m/40,000 = ₦3,250.
If the selling price is ₦4,500 a unit, the break-even output is F/(p − v) = 50 m/2,500 = 20,000 units (check: revenue 20,000 × 4,500 = ₦90 m = 50 m + 2,000 × 20,000 ✓).
Running near full capacity spreads fixed costs and lowers unit cost; that is why capacity utilisation matters.
Oil and gas operating costs
Often expressed as cost per barrel of oil equivalent (US$/boe): lifting cost, transport, processing, security (a major cost in parts of the Niger Delta), host community obligations and regulatory levies under the Petroleum Industry Act 2021.
Contingency
Contingency is money added to an estimate for uncertain items within the scope that experience says will occur but cannot yet be identified: incomplete design detail, quantity growth, price uncertainty within the market, minor errors.
- Typical contingency falls as the estimate class improves: perhaps 25-40% at concept stage, 10-15% at the budget stage and 5-10% for a definitive estimate (guides only).
- It is not for changes of scope, major disasters or strikes (those are management reserve or insurance).
- Better: set contingency by risk analysis: list risks with probabilities and cost impacts, or run a Monte Carlo simulation and choose, for example, the P80 value (an 80% chance of not being exceeded).
Example (expected-value method): risk A, 30% chance, ₦10 m; risk B, 10% chance, ₦40 m; risk C, 50% chance, ₦4 m. Expected cost = 3 + 4 + 2 = ₦9 million: a starting point for contingency.
Allowances
Allowances are amounts for known items whose quantity or cost is not yet fully defined: for example, an allowance for cable trays before the cable routing is designed, for small-bore piping, for wastage and offcuts (say 5% on steel bars), for weather downtime on site, or for import duties.
They are part of the base estimate, unlike contingency.
Escalation
An allowance for price rises over time between the estimate date and when the money is spent: (inflation rate) × (time to mid-point of spending). Example: ₦1 billion of work spent mainly in 2 years' time at 20% a year inflation: about 1 × (1.2² − 1) = ₦440 million of escalation if spent at the end of year 2; less if spread out. Use separate rates for imported (foreign currency) and local items.
Exams usually ask
- Classify operating costs into fixed and variable and compute unit cost and break-even.
- Distinguish contingency, allowances and escalation.
- Explain how contingency can be estimated from risks.
Common mistake
Using contingency to pay for new work the client adds. That is a scope change and must be priced and approved separately.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Best pick Operating expense
(opens en.wikipedia.org in a new tab)
Wikipedia, Operating expense, CC BY-SA 4.0 · licence
-
Cost contingency
(opens en.wikipedia.org in a new tab)
Wikipedia, Cost contingency, CC BY-SA 4.0 · licence
-
OpenStax, Principles of Management (whole free textbook)
The whole book, free to read online or download as a PDF (the PDF is large: Wi-Fi).
(opens openstax.org in a new tab)
OpenStax, OpenStax, Principles of Management (whole free textbook), CC BY-NC-SA 4.0 · licence
Watch
-
Ep 07 Understanding Cash Allowances and Contingency Allowances
15 min · ≈ 68 MB · about ₦38
(opens youtube.com in a new tab)
-
Contingency vs Allowance
5 min · ≈ 23 MB · about ₦13
(opens youtube.com in a new tab)
-
Contingency vs Risk Allowance | What's the Difference?
9 min · ≈ 41 MB · about ₦23
(opens youtube.com in a new tab)
-
Alignment of Contingency Definition and Concepts - Part II - Allowance and management reserve
4 min · ≈ 18 MB · about ₦10
(opens youtube.com in a new tab)
We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.