ENG 502 · Engineering Management
Our notes
2 min readWhy plan
Most project failures (late, over budget, poor quality) trace back to poor planning: unclear scope, unrealistic estimates, ignored risks.
The project triangle
Scope, time and cost (with quality in the middle) are linked: changing one affects the others. Adding work without adding time or money lowers quality or fails the project.
Steps in project planning
- Define objectives and scope: what will be delivered, and what will not (exclusions). A scope statement or project charter is approved by the sponsor.
- Work breakdown structure (WBS): break the project into deliverables and then into work packages small enough to estimate, assign and control.
- Activities and sequence: list activities for each work package and their dependencies.
- Estimate durations and resources (people, equipment, materials).
- Schedule: network and critical path (CPM/PERT, as in ENG 501), bar chart, milestones.
- Cost estimate and budget (cost engineering topics), spread over time as a cost baseline (S-curve).
- Responsibility assignment: who does what.
- Risk plan: identify risks, assess, plan responses.
- Quality, procurement, communication and HSE plans.
- Approve the baseline (scope, time, cost) against which progress is controlled.
Example: WBS for a small gas metering station
- Project management
- Engineering: 2.1 process design; 2.2 civil and structural design; 2.3 electrical and instrumentation design
- Procurement: 3.1 meters and valves; 3.2 piping; 3.3 cables and panels
- Construction: 4.1 site preparation; 4.2 foundations; 4.3 mechanical installation; 4.4 electrical installation
- Commissioning: 5.1 pressure testing; 5.2 calibration; 5.3 handover
The 100% rule: the WBS includes all the work, and only the work, in the scope.
Responsibility assignment matrix (RACI)
For each work package, mark who is Responsible (does it), Accountable (owns it, one person), Consulted and Informed.
| Work package | Project manager | Process engineer | Procurement | Client |
|---|---|---|---|---|
| 2.1 Process design | A | R | I | C |
| 3.1 Meters and valves | A | C | R | I |
| 5.3 Handover | R | C | I | A |
Resource planning
Plot resource needs over time (a histogram). Peaks may be smoothed by moving non-critical activities within their float (resource levelling), which avoids hiring and firing and overloading equipment.
Planning for uncertainty
Use ranges and PERT estimates, add contingency (later topic), and plan phases with decision gates (concept, feasibility, FEED, execution), so that money is committed in steps as information improves.
Exams usually ask
- Describe the steps in planning an engineering project.
- Draw a work breakdown structure for a given project.
- Explain a responsibility matrix and resource levelling.
Common mistake
Making the WBS a list of departments. It should break down the deliverables (what is produced), not the organisation.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Best pick Principles of Management, 17.2 The Planning Process
(opens openstax.org in a new tab)
OpenStax, Principles of Management, 17.2 The Planning Process, CC BY-NC-SA 4.0 · licence
-
Project planning
(opens en.wikipedia.org in a new tab)
Wikipedia, Project planning, CC BY-SA 4.0 · licence
-
Work breakdown structure
(opens en.wikipedia.org in a new tab)
Wikipedia, Work breakdown structure, CC BY-SA 4.0 · licence
-
Critical path method
(opens en.wikipedia.org in a new tab)
Wikipedia, Critical path method, CC BY-SA 4.0 · licence
-
OpenStax, Principles of Management (whole free textbook)
The whole book, free to read online or download as a PDF (the PDF is large: Wi-Fi).
(opens openstax.org in a new tab)
OpenStax, OpenStax, Principles of Management (whole free textbook), CC BY-NC-SA 4.0 · licence
Watch
-
Project Planning: Plan Your Project - PM Fundamentals
12 min · ≈ 54 MB · about ₦30
(opens youtube.com in a new tab)
-
What is Engineering Management? | Differences between Project Management and Engineering Management
4 min · ≈ 18 MB · about ₦10
(opens youtube.com in a new tab)
-
Project Planning for Beginners - Project Management Training
6 min · ≈ 27 MB · about ₦15
(opens youtube.com in a new tab)
-
What is Project Planning? | Project Management Phases | Invensis Learning
22 min · ≈ 99 MB · about ₦56
(opens youtube.com in a new tab)
-
Project Planning and Management Lecture One
1 h 1 min · ≈ 275 MB · about ₦154
(opens youtube.com in a new tab)
We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.