ENG 501 · Professional Practice and Procedures
Our notes
2 min readStages of an engineering design project
- Brief and requirements: what must the product or facility do? Constraints (budget, codes, site).
- Conceptual design: generate and compare alternatives (sketches, rough sizing, cost estimates); choose one.
- Preliminary (basic, front-end) design: main dimensions, layouts, process flow diagrams, key equipment; refined cost estimate. In oil and gas this is FEED (front-end engineering design).
- Detailed design: full calculations, drawings, specifications (materials and workmanship), bills of quantities, equipment data sheets.
- Design review and checking: independent checking, hazard studies (HAZOP for process plants), approval by the client and regulators.
- Construction support: answering site queries, approving shop drawings, changes.
- As-built records at handover.
Project scheduling
Bar (Gantt) charts
Each activity is a horizontal bar against time. Easy to read and to show progress; but they do not show clearly which activities depend on others.
The critical path method (CPM)
- List activities, durations and dependencies.
- Draw the network (activity-on-node).
- Forward pass: earliest start (ES) and finish (EF = ES + duration); an activity starts at the latest EF of its predecessors.
- Backward pass: latest finish (LF) and start (LS = LF − duration); an activity's LF is the earliest LS of its successors.
- Total float = LS − ES. Activities with zero float are critical; the chain of them is the critical path, which fixes the project duration.
Worked example (durations in weeks)
| Activity | Duration | Depends on |
|---|---|---|
| A Site survey | 3 | — |
| B Order equipment | 4 | — |
| C Foundations | 2 | A |
| D Access road | 5 | A |
| E Install equipment | 3 | B, C |
| F Commissioning | 2 | D, E |
Forward pass: A 0-3; B 0-4; C 3-5; D 3-8; E starts at max(4, 5) = 5, ends 8; F starts at max(8, 8) = 8, ends 10.
Backward pass (from 10): F 8-10; D LF 8, LS 3; E LF 8, LS 5; C LF 5, LS 3; B LF 5, LS 1; A LF = min(3, 3) = 3, LS 0.
Floats: A 0, B 1, C 0, D 0, E 0, F 0.
Critical paths: A-D-F (3 + 5 + 2 = 10) and A-C-E-F (3 + 2 + 3 + 2 = 10). Only B can slip (by 1 week) without delaying the project.
Check: the longest path through the network is 10 weeks; B-E-F is 4 + 3 + 2 = 9, giving B its 1 week of float ✓.
PERT (uncertain durations)
For each activity estimate optimistic a, most likely m and pessimistic b times:
- Expected time t_e = (a + 4m + b)/6; standard deviation σ = (b − a)/6.
- Example: a = 2, m = 4, b = 12 weeks: t_e = (2 + 16 + 12)/6 = 5 weeks, σ = 10/6 ≈ 1.67 weeks.
- Add t_e and variances along the critical path to estimate the chance of finishing by a target date (using the normal distribution).
Resources and crashing
Levelling resources (labour, cranes) and crashing (spending more to shorten critical activities) are covered in ENG 502. Software (Microsoft Project, Primavera P6) is used in practice.
Exams usually ask
- Describe the stages of an engineering design project.
- Draw a network, find the critical path, project duration and floats.
- Calculate PERT expected times and standard deviations.
Common mistake
Taking the earliest start of an activity from only one predecessor. It must wait for all its predecessors: use the latest of their finish times.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Best pick Principles of Management, 17.2 The Planning Process
(opens openstax.org in a new tab)
OpenStax, Principles of Management, 17.2 The Planning Process, CC BY-NC-SA 4.0 · licence
-
Engineering design process
(opens en.wikipedia.org in a new tab)
Wikipedia, Engineering design process, CC BY-SA 4.0 · licence
-
Gantt chart
(opens en.wikipedia.org in a new tab)
Wikipedia, Gantt chart, CC BY-SA 4.0 · licence
-
Schedule (project management)
(opens en.wikipedia.org in a new tab)
Wikipedia, Schedule (project management), CC BY-SA 4.0 · licence
Watch
-
How to Create a Project Schedule - 21 Steps in 5 Stages
8 min · ≈ 36 MB · about ₦20
(opens youtube.com in a new tab)
-
Project Scheduling - PERT/CPM | Finding Critical Path
7 min · ≈ 32 MB · about ₦18
(opens youtube.com in a new tab)
-
What is Project Scheduling? - Project Management Training
3 min · ≈ 14 MB · about ₦8
(opens youtube.com in a new tab)
-
Project Planning and Design Introduction
6 min · ≈ 27 MB · about ₦15
(opens youtube.com in a new tab)
-
Project Management Concepts and People Issues - Project Scheduling & Tracking - Software Engineering
48 min · ≈ 216 MB · about ₦121
(opens youtube.com in a new tab)
We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.