2 min readFortescue's theorem (1918)
Any set of three unbalanced phasors can be written as the sum of three balanced sets:
- Positive sequence (1): three equal phasors 120° apart, in the normal phase order a-b-c.
- Negative sequence (2): three equal phasors 120° apart, in the reverse order a-c-b.
- Zero sequence (0): three equal phasors in phase.
The operator a
a = 1∠120° = −0.5 + j0.866. Properties: a² = 1∠240° = −0.5 − j0.866, a³ = 1, and 1 + a + a² = 0.
Transformations
Phase from sequence:
- I_a = I0 + I1 + I2
- I_b = I0 + a²I1 + aI2
- I_c = I0 + aI1 + a²I2
Sequence from phase:
- I0 = (1/3)(I_a + I_b + I_c)
- I1 = (1/3)(I_a + aI_b + a²I_c)
- I2 = (1/3)(I_a + a²I_b + aI_c)
Worked example
I_a = 10∠0°, I_b = 10∠180° (= −10), I_c = 0 (a line-to-line current pattern).
- I0 = (1/3)(10 − 10 + 0) = 0.
- I1 = (1/3)(10 + a(−10)) = (1/3)(10 + 5 − j8.66) = 5 − j2.887 = 5.774∠−30°.
- I2 = (1/3)(10 + a²(−10)) = (1/3)(10 + 5 + j8.66) = 5 + j2.887 = 5.774∠30°.
Check: I_a = 0 + (5 − j2.887) + (5 + j2.887) = 10 ✓. I_b = a²I1 + aI2 = 5.774∠−150° + 5.774∠150° = (−5 − j2.887) + (−5 + j2.887) = −10 ✓.
Useful facts
- Zero-sequence current flows only if there is a return path: I_n = 3I0 in the neutral. A delta winding or ungrounded star blocks it from the lines.
- A balanced system has only positive sequence; negative sequence indicates unbalance (it heats rotors of machines, so generators have negative-sequence protection).
Sequence impedances
- Lines: Z1 = Z2; Z0 is larger (typically 2 to 3.5 times) because of ground return.
- Transformers: Z1 = Z2 = Z0 (leakage) but the zero-sequence path depends on connections: grounded star to delta passes zero sequence on the star side only.
- Generators: Z1, Z2 and Z0 all different; Z0 is small; a neutral impedance Z_n appears as 3Z_n in the zero-sequence network.
Sequence networks
Each sequence has its own network; only the positive-sequence network contains sources (generators produce balanced positive-sequence voltages). Unbalanced faults are solved by connecting the three networks at the fault point in ways set by the fault type (next topics).
Exams usually ask: state Fortescue's theorem; prove 1 + a + a² = 0; resolve unbalanced phasors into sequence components; explain zero-sequence paths through transformer connections.
Common mistake: forgetting the factor 1/3 when finding sequence components, or using a where a² belongs. Check by rebuilding the phase values.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Symmetrical components
(opens en.wikipedia.org in a new tab)
Wikipedia, Symmetrical components, CC BY-SA 4.0 · licence
-
MIT 6.061 Introduction to Electric Power Systems (whole course)
Lecture notes, problem sets and exams as PDFs: per unit, transmission lines, load flow, faults (harder than our notes).
(opens ocw.mit.edu in a new tab)
MIT OpenCourseWare, MIT 6.061 Introduction to Electric Power Systems (whole course), CC BY-NC-SA 4.0 · licence
Watch
-
Best pick Introduction of Symmetrical Components - Symmetrical Components - Power System 2
5 min · ≈ 23 MB · about ₦13
(opens youtube.com in a new tab)
-
What is 'a' Operator? | Symmetrical Components and Asymmetrical Fault Analysis
9 min · ≈ 41 MB · about ₦23
(opens youtube.com in a new tab)
-
SYMMETRICAL COMPONENT TRANSFORMATION / KTU/ POWER SYSTEM ANALYSIS
22 min · ≈ 99 MB · about ₦56
(opens youtube.com in a new tab)
-
Sequence Impedances of Transmission Line - Symmetrical Components - Power System 2
13 min · ≈ 59 MB · about ₦33
(opens youtube.com in a new tab)
-
Lecture -26 Symmetrical Component Analysis
1 h · ≈ 270 MB · about ₦152
(opens youtube.com in a new tab)
-
Lecture -27 Sequence Networks
1 h · ≈ 270 MB · about ₦152
(opens youtube.com in a new tab)
-
Sequence Networks of Generator, Transformer, Transmission Line
28 min · ≈ 126 MB · about ₦71
(opens youtube.com in a new tab)
We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.