MEG 508 · Power Plant Engineering
Our notes
2 min readMethods of generating electricity
| Plant | Energy conversion | Typical role |
|---|---|---|
| Steam (coal, gas, oil, biomass, nuclear) | heat → steam → turbine → generator | base load |
| Gas turbine (open cycle) | fuel combustion → hot gas → turbine | peak load, fast start |
| Combined cycle | gas turbine + heat recovery steam cycle | base and intermediate |
| Diesel/gas engines | internal combustion | small plants, standby, islands |
| Hydro | potential energy of water → turbine | base or peak (storage) |
| Solar PV | light → electricity directly | daytime, variable |
| Wind | kinetic energy of air → turbine | variable |
| Geothermal | earth heat → steam | base load |
Most use a turbine driving an alternator (synchronous generator); Nigeria's grid frequency is 50 Hz, so a 2-pole generator turns at 3,000 rpm.
Load curves
- Load curve: demand against time of day.
- Load duration curve: loads arranged from highest to lowest; area = energy.
- Base load (always present), intermediate, peak load (short periods).
Base load suits plants with low running cost (hydro, nuclear, efficient steam/combined cycle); peak load suits plants with low capital cost and fast start (open-cycle gas turbines, diesel, pumped storage).
Performance factors
- Load factor = average load ÷ peak load (over a period).
- Capacity (plant) factor = actual energy ÷ (rated capacity × hours).
- Demand factor = maximum demand ÷ connected load.
- Diversity factor = sum of individual maximum demands ÷ maximum demand of the whole system (≥ 1): consumers do not peak together.
- Utilisation factor = maximum demand ÷ rated plant capacity.
- Reserve capacity = installed capacity − maximum demand.
Worked example
A plant rated 100 MW has a peak load of 80 MW and generates 438 GWh in a year.
Average load = 438,000 MWh/8,760 h = 50 MW.
Load factor = 50/80 = 0.625. Capacity factor = 50/100 = 0.50. Utilisation factor = 80/100 = 0.80.
If the consumers' individual maximum demands add up to 100 MW, the diversity factor = 100/80 = 1.25.
Choosing the plant mix
Consider fuel availability (Nigeria has large gas reserves), capital and running costs, load shape, location (near load, water, fuel, transmission), environmental impact, reliability and grid stability.
Exams usually ask
- Define load factor, capacity factor, diversity factor and utilisation factor; solve problems.
- Sketch load and load duration curves and explain base and peak load plants.
- Compare methods of power generation.
Common mistake
Confusing load factor with capacity factor. Load factor compares average with peak load; capacity factor compares average with rated capacity.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Electricity generation
(opens en.wikipedia.org in a new tab)
Wikipedia, Electricity generation, CC BY-SA 4.0 · licence
-
Load factor (electrical)
(opens en.wikipedia.org in a new tab)
Wikipedia, Load factor (electrical), CC BY-SA 4.0 · licence
-
Capacity factor
(opens en.wikipedia.org in a new tab)
Wikipedia, Capacity factor, CC BY-SA 4.0 · licence
Watch
-
Best pick Load Factor, Diversity Factor and Plant Factor | Factors of Economic Power Generation
9 min · ≈ 41 MB · about ₦23
(opens youtube.com in a new tab)
-
Load Curve
11 min · ≈ 50 MB · about ₦28
(opens youtube.com in a new tab)
-
PS120 Load Curve, Load Duration Curve, Integrated Load Duration Curve, Mass Curve
19 min · ≈ 86 MB · about ₦48
(opens youtube.com in a new tab)
-
Load Curves and Related Factors of Power Systems
29 min · ≈ 131 MB · about ₦74
(opens youtube.com in a new tab)
-
Plant Factors and Load Duration Curve
30 min · ≈ 135 MB · about ₦76
(opens youtube.com in a new tab)
We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.