Costs of a power plant

  • Capital (fixed) costs: land, buildings, equipment, installation, interest during construction. Expressed per kW of capacity (₦/kW or US$/kW).
  • Fixed annual costs: interest on capital, depreciation, insurance, taxes, fixed staff and maintenance: incurred whether or not the plant runs.
  • Variable (running) costs: fuel (the largest for thermal plants), variable maintenance, consumables: depend on energy generated.

Hydro: high capital, very low running cost. Gas turbine: low capital, high fuel cost.

Annual cost and cost per kWh

Annual cost = fixed cost + variable cost × energy. Cost per kWh = annual cost ÷ kWh generated: falls as the load factor rises because fixed costs are spread over more energy.

Worked example: capital recovery

A plant costs US$1,000 per kW; interest 10%; life 25 years.
Capital recovery factor CRF = i(1 + i)ⁿ/((1 + i)ⁿ − 1) = 0.1 × 10.835/9.835 = 0.1102.
Annual capital charge = 1,000 × 0.1102 = US$110.2 per kW per year.
At a capacity factor of 0.8 the plant generates 0.8 × 8,760 = 7,008 kWh per kW per year, so capital cost per kWh = 110.2/7,008 = 1.57 US cents/kWh. At 0.4 it doubles to 3.14 cents.

Heat rate and fuel cost

Heat rate = heat input per kWh = 3,600/η (kJ/kWh).
At η = 35%: heat rate = 10,286 kJ/kWh (about 9.75 MMBtu per MWh, using 1 MMBtu = 1,055,056 kJ).
Fuel cost per kWh = heat rate × fuel price. Gas at US$3 per MMBtu: 10,286/1,055,056 × 3 = US$0.029 per kWh (2.9 cents).

Levelised cost of electricity (LCOE)

Total lifetime cost (discounted) ÷ total lifetime energy (discounted): compares technologies fairly. Solar and onshore wind are now among the cheapest new sources in many countries; storage adds cost.

Tariffs

  • Flat rate, block rate, two-part tariff (a demand/fixed charge per kW plus an energy charge per kWh), time-of-use, prepaid.
  • In Nigeria NERC sets tariffs through the Multi-Year Tariff Order (MYTO); since 2024 customers are grouped into service bands (Band A for at least 20 hours of supply a day pays the highest rate); check current tariffs.
  • Problems: tariffs below cost-reflective levels, collection losses, estimated billing (metering gap).

Choosing plants

Compare LCOE, capacity factor, flexibility, fuel security, construction time, environmental cost and grid needs. A mix is used: low running cost plants for base load, cheap-to-build plants for peaks.

Depreciation methods

  • Straight line: (cost − salvage)/life each year.
  • Sinking fund: set aside an annual amount that grows with interest to replace the plant.
  • Diminishing balance: a fixed percentage of the remaining value.

Exams usually ask

  • Distinguish fixed and variable costs; calculate the cost of generation per kWh at different load factors.
  • Calculate heat rate and fuel cost per kWh.
  • Explain the types of tariff and discuss electricity pricing in Nigeria.

Common mistake

Comparing plants on capital cost alone. A cheap-to-build plant with expensive fuel can cost more per kWh over its life than a costly hydro plant.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All MEG 508 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.