Public projects, budgets and budget control

How public projects differ, benefit-cost analysis, the social discount rate, budgets, variances and earned value for controlling project costs.

Our notes

2 min read

Public projects

Roads, bridges, water schemes, power, hospitals, flood control. They differ from private projects:

  • Benefits go to the public (time saved, fewer accidents, health) and are often hard to price.
  • Disbenefits (pollution, displacement, noise) must be counted too.
  • Long lives (30-50 years and more); financed by taxes, bonds or donors; decisions involve politics and many stakeholders.
  • A lower social discount rate is used (because society cares about the long run), which favours projects with long-term benefits.

Benefit-cost analysis

B/C = PW(benefits − disbenefits)/PW(costs). Accept if B/C ≥ 1.

  • Conventional B/C: operating and maintenance costs go with the costs (denominator).
  • Modified B/C: O&M costs are subtracted from the benefits (numerator). Both give the same accept/reject decision, not always the same ratio.

Worked example. A road costs ₦500 million, gives benefits of ₦80 million a year (time and vehicle costs saved) for 20 years, and costs ₦10 million a year to maintain; i = 8%. (P/A, 8%, 20) = 3.66096/0.37288 = 9.8181.
PW benefits = 80 × 9.8181 = ₦785.4 million; PW maintenance = 98.2 million.
Conventional B/C = 785.4/(500 + 98.2) = 1.31; modified B/C = (785.4 − 98.2)/500 = 1.37. Both above 1: the road is justified.

  • Incremental B/C for choosing between projects (as with incremental IRR).
  • Difficulties: putting values on time, life and environment; deciding who counts as "the public"; risk of inflating benefits to win approval.

Budgets

A budget is a plan in money for a period or project: what will be spent, on what, and when.

  • Capital budget: investments (new plant, equipment); projects ranked by PW, IRR or B/C, within the money available (capital rationing: choose the combination with the highest total PW).
  • Operating budget: day-to-day running costs and revenues.
  • Project budget: cost estimate broken into work packages, with a time-phased plan (the S-curve of cumulative planned cost).

Budget control

Compare actual with planned, find the reasons for the differences (variances), and act.

  • Variance = budgeted − actual (negative = overspend). A ₦10 million budget with ₦11.5 million spent: −₦1.5 million, 15% over.
  • Earned value management: Planned value (PV: budgeted cost of work scheduled), Earned value (EV: budgeted cost of work actually done), Actual cost (AC).
  • Cost variance CV = EV − AC; cost performance index CPI = EV/AC.
  • Schedule variance SV = EV − PV; schedule performance index SPI = EV/PV.

Worked example. By month 6 a project planned to do ₦40 million of work; work worth ₦35 million is done, at an actual cost of ₦42 million. CPI = 35/42 = 0.83 (getting ₦0.83 of work per naira spent); SPI = 35/40 = 0.875 (behind schedule). If the total budget is ₦100 million and the CPI stays the same, the estimate at completion = 100/0.833 = ₦120 million.

  • Controls: approvals for changes, contingency reserves, regular reports, and early action on trends (a CPI falling below 1 rarely recovers by itself).

Exams usually ask: features of public projects; benefit-cost ratio (conventional and modified) with a calculation; social discount rate; types of budgets and capital rationing; variances and earned value calculations.

Common mistake: treating SPI below 1 as "over budget". SPI measures schedule (behind or ahead); CPI measures cost (over or under budget).

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

We link to free material and never copy it. Every link was opened by our team before it went up.

All ENG 402 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.