ENG 402 · Engineering Economics
Our notes
2 min readPublic projects
Roads, bridges, water schemes, power, hospitals, flood control. They differ from private projects:
- Benefits go to the public (time saved, fewer accidents, health) and are often hard to price.
- Disbenefits (pollution, displacement, noise) must be counted too.
- Long lives (30-50 years and more); financed by taxes, bonds or donors; decisions involve politics and many stakeholders.
- A lower social discount rate is used (because society cares about the long run), which favours projects with long-term benefits.
Benefit-cost analysis
B/C = PW(benefits − disbenefits)/PW(costs). Accept if B/C ≥ 1.
- Conventional B/C: operating and maintenance costs go with the costs (denominator).
- Modified B/C: O&M costs are subtracted from the benefits (numerator). Both give the same accept/reject decision, not always the same ratio.
Worked example. A road costs ₦500 million, gives benefits of ₦80 million a year (time and vehicle costs saved) for 20 years, and costs ₦10 million a year to maintain; i = 8%. (P/A, 8%, 20) = 3.66096/0.37288 = 9.8181.
PW benefits = 80 × 9.8181 = ₦785.4 million; PW maintenance = 98.2 million.
Conventional B/C = 785.4/(500 + 98.2) = 1.31; modified B/C = (785.4 − 98.2)/500 = 1.37. Both above 1: the road is justified.
- Incremental B/C for choosing between projects (as with incremental IRR).
- Difficulties: putting values on time, life and environment; deciding who counts as "the public"; risk of inflating benefits to win approval.
Budgets
A budget is a plan in money for a period or project: what will be spent, on what, and when.
- Capital budget: investments (new plant, equipment); projects ranked by PW, IRR or B/C, within the money available (capital rationing: choose the combination with the highest total PW).
- Operating budget: day-to-day running costs and revenues.
- Project budget: cost estimate broken into work packages, with a time-phased plan (the S-curve of cumulative planned cost).
Budget control
Compare actual with planned, find the reasons for the differences (variances), and act.
- Variance = budgeted − actual (negative = overspend). A ₦10 million budget with ₦11.5 million spent: −₦1.5 million, 15% over.
- Earned value management: Planned value (PV: budgeted cost of work scheduled), Earned value (EV: budgeted cost of work actually done), Actual cost (AC).
- Cost variance CV = EV − AC; cost performance index CPI = EV/AC.
- Schedule variance SV = EV − PV; schedule performance index SPI = EV/PV.
Worked example. By month 6 a project planned to do ₦40 million of work; work worth ₦35 million is done, at an actual cost of ₦42 million. CPI = 35/42 = 0.83 (getting ₦0.83 of work per naira spent); SPI = 35/40 = 0.875 (behind schedule). If the total budget is ₦100 million and the CPI stays the same, the estimate at completion = 100/0.833 = ₦120 million.
- Controls: approvals for changes, contingency reserves, regular reports, and early action on trends (a CPI falling below 1 rarely recovers by itself).
Exams usually ask: features of public projects; benefit-cost ratio (conventional and modified) with a calculation; social discount rate; types of budgets and capital rationing; variances and earned value calculations.
Common mistake: treating SPI below 1 as "over budget". SPI measures schedule (behind or ahead); CPI measures cost (over or under budget).
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Best pick Principles of Accounting, Volume 2: Managerial Accounting, 7.1 Describe How and Why Managers Use Budgets
(opens openstax.org in a new tab)
OpenStax, Principles of Accounting, Volume 2: Managerial Accounting, 7.1 Describe How and Why Managers Use Budgets, CC BY-NC-SA 4.0 · licence
-
Benefit–cost ratio
(opens en.wikipedia.org in a new tab)
Wikipedia, Benefit–cost ratio, CC BY-SA 4.0 · licence
-
Principles of Accounting, Volume 2: Managerial Accounting, 7.4 Prepare Flexible Budgets
(opens openstax.org in a new tab)
OpenStax, Principles of Accounting, Volume 2: Managerial Accounting, 7.4 Prepare Flexible Budgets, CC BY-NC-SA 4.0 · licence
-
Principles of Accounting, Volume 2: Managerial Accounting, 7.5 Explain How Budgets Are Used to Evaluate Goals
(opens openstax.org in a new tab)
OpenStax, Principles of Accounting, Volume 2: Managerial Accounting, 7.5 Explain How Budgets Are Used to Evaluate Goals, CC BY-NC-SA 4.0 · licence
-
Cost–benefit analysis
(opens en.wikipedia.org in a new tab)
Wikipedia, Cost–benefit analysis, CC BY-SA 4.0 · licence
-
Budget
(opens en.wikipedia.org in a new tab)
Wikipedia, Budget, CC BY-SA 4.0 · licence
We link to free material and never copy it. Every link was opened by our team before it went up.