ENG 402 · Engineering Economics
Our notes
3 min readFeasibility study
A study done before committing money, to decide whether a project should go ahead. Parts:
- Market (demand) study: who will buy, how much, at what price, competitors.
- Technical study: process, equipment, site, raw materials, power and water supply, capacity, staffing.
- Financial and economic study: investment cost, operating costs, revenues, financing, cash flow tables, PW, IRR, payback, break-even.
- Environmental and social study: impacts, permits (an Environmental Impact Assessment is required by law for many projects in Nigeria), community relations (very important in the Niger Delta).
- Legal and organisational: company registration (CAC), licences, regulations, management.
- Risk analysis and recommendation.
Pre-feasibility studies screen ideas cheaply; the full feasibility study goes deeper on the promising ones; a bankable study is one a lender will accept.
Dealing with uncertainty
- Sensitivity analysis: change one estimate at a time (price, cost, life, MARR, exchange rate) and see how the PW changes. Worked example. For the project investing ₦1,000,000 for ₦300,000 a year over 5 years at 10% (PW +₦137,240): if annual returns fall 20% to ₦240,000, PW = 240,000 × 3.7908 − 1,000,000 = −₦90,208; if they rise 20%, PW = +₦364,688. The decision is sensitive to returns: firm up that estimate first.
- Break-even value of a variable: the value at which PW = 0. Annual returns must be at least 1,000,000/3.7908 = ₦263,797.
- Scenario analysis: pessimistic, most likely and optimistic sets of estimates together.
- Probability and expected value: E(PW) = Σ p × PW; decision trees; Monte Carlo simulation draws random values for uncertain inputs thousands of times to give a distribution of PW.
Spreadsheet functions (Excel, Google Sheets, LibreOffice)
| Function | Gives |
|---|---|
| =PV(rate, nper, pmt, [fv]) | present worth of a series (sign convention: money paid is negative) |
| =FV(rate, nper, pmt, [pv]) | future worth |
| =PMT(rate, nper, pv) | equal payment (loan repayment, capital recovery) |
| =NPV(rate, values) | PW of values at end of years 1, 2, … (add the year-0 cash flow separately) |
| =IRR(values) | internal rate of return of a cash flow list (year 0 included) |
| =XNPV, =XIRR | the same with actual dates |
| =RATE(nper, pmt, pv) | interest rate of an annuity |
| =NPER(rate, pmt, pv) | number of periods |
| =SLN, =DDB, =SYD | depreciation by straight-line, double declining and sum-of-years' digits |
Worked example. With year 0 in B1 (−1000000) and years 1-5 in B2:B6 (300000 each): =B1+NPV(10%,B2:B6) gives 137,236 (factors not rounded); =IRR(B1:B6) gives 15.24%. =PMT(15%,4,-2000000) gives 700,530, the loan repayment found earlier.
- Data tables and Goal Seek do sensitivity and break-even values quickly; charts of PW against each variable (a "spider" plot) show which matter most.
- Keep inputs (rates, prices, quantities) in labelled cells and refer to them, so the model updates when an estimate changes; never type numbers into formulas.
Writing up
State the assumptions (rates, prices, exchange rate, dates), show the cash flow table, the results by more than one criterion, the sensitivity results, the non-money factors, and a clear recommendation.
Exams usually ask: the parts of a feasibility study; sensitivity, scenario and break-even analysis; expected value and decision trees in outline; spreadsheet functions for PW, IRR and loan payments (and the NPV year-0 trap).
Common mistake: putting the year-0 investment inside Excel's NPV range. NPV() treats its first value as one year away, so it discounts the investment too; add year 0 outside the function.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Best pick Principles of Finance, 16.6 Using Excel to Make Company Investment Decisions
(opens openstax.org in a new tab)
OpenStax, Principles of Finance, 16.6 Using Excel to Make Company Investment Decisions, CC BY-NC-SA 4.0 · licence
-
Principles of Finance, 16.5 Choosing between Projects
(opens openstax.org in a new tab)
OpenStax, Principles of Finance, 16.5 Choosing between Projects, CC BY-NC-SA 4.0 · licence
-
Principles of Finance, 8.5 Equal Payments with a Financial Calculator and Excel
(opens openstax.org in a new tab)
OpenStax, Principles of Finance, 8.5 Equal Payments with a Financial Calculator and Excel, CC BY-NC-SA 4.0 · licence
-
Feasibility study
(opens en.wikipedia.org in a new tab)
Wikipedia, Feasibility study, CC BY-SA 4.0 · licence
-
Sensitivity analysis
(opens en.wikipedia.org in a new tab)
Wikipedia, Sensitivity analysis, CC BY-SA 4.0 · licence