Project scheduling with CPM and PERT

Networks, forward and backward passes, floats, the critical path, and PERT probabilities.

Our notes

2 min read

Why network scheduling

Engineering projects (a plant shutdown, a building, a pipeline) have many activities with precedence. CPM (Critical Path Method) and PERT (Program Evaluation and Review Technique) find the shortest project time and which activities control it.

Network terms

  • Activity: a task that takes time.
  • Predecessor: must finish first.
  • Activity-on-node network: boxes for activities, arrows for precedence.

Worked example

ActivityDepends onDays
Anone3
Bnone4
CA2
DA5
EB, C3
FD, E2

Forward pass (earliest start ES, earliest finish EF = ES + duration):

Act.ESEF
A03
B04
C35
D38
Emax(4, 5) = 58
Fmax(8, 8) = 810

Project time = 10 days.

Backward pass (latest finish LF, latest start LS = LF − duration):

Act.LFLSFloat = LS − ES
F1080
E850
D830
C530
B511
Amin(3, 3) = 300

Critical paths (zero float): A-D-F (3 + 5 + 2 = 10) and A-C-E-F (3 + 2 + 3 + 2 = 10). Two critical paths.
Check: path B-E-F = 4 + 3 + 2 = 9 days, one less than 10, matching B's float of 1.

Floats

  • Total float: how long an activity can slip without delaying the project.
  • Free float: how long it can slip without delaying any following activity.

PERT: uncertain durations

Each activity has three estimates: optimistic a, most likely m, pessimistic b.

  • Expected time tₑ = (a + 4m + b) ÷ 6.
  • Variance σ² = ((b − a) ÷ 6)².

Example: a = 2, m = 4, b = 12 → tₑ = (2 + 16 + 12) ÷ 6 = 5 days; σ² = (10 ÷ 6)² ≈ 2.78.

Probability of finishing on time

Add the expected times and the variances along the critical path; assume the total is roughly normal.
A project with expected time 30 days and standard deviation 2 days: P(finish within 33 days) → z = (33 − 30) ÷ 2 = 1.5 → about 93%.
Check: from tables, the area below z = 1.5 is 0.9332.

Crashing

Shortening activities by adding resources at extra cost. Crash the cheapest critical activity per day first, and watch for new critical paths. When two paths are critical (as above), both must be shortened together.

Exams usually ask

  • Draw a network, do forward and backward passes, and find the critical path.
  • Calculate PERT expected times and a completion probability.

Common mistake

Taking the earliest finish of only one predecessor. An activity starts after all its predecessors finish: use the maximum.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All ENG 401 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.