2 min readWhy network scheduling
Engineering projects (a plant shutdown, a building, a pipeline) have many activities with precedence. CPM (Critical Path Method) and PERT (Program Evaluation and Review Technique) find the shortest project time and which activities control it.
Network terms
- Activity: a task that takes time.
- Predecessor: must finish first.
- Activity-on-node network: boxes for activities, arrows for precedence.
Worked example
| Activity | Depends on | Days |
|---|---|---|
| A | none | 3 |
| B | none | 4 |
| C | A | 2 |
| D | A | 5 |
| E | B, C | 3 |
| F | D, E | 2 |
Forward pass (earliest start ES, earliest finish EF = ES + duration):
| Act. | ES | EF |
|---|---|---|
| A | 0 | 3 |
| B | 0 | 4 |
| C | 3 | 5 |
| D | 3 | 8 |
| E | max(4, 5) = 5 | 8 |
| F | max(8, 8) = 8 | 10 |
Project time = 10 days.
Backward pass (latest finish LF, latest start LS = LF − duration):
| Act. | LF | LS | Float = LS − ES |
|---|---|---|---|
| F | 10 | 8 | 0 |
| E | 8 | 5 | 0 |
| D | 8 | 3 | 0 |
| C | 5 | 3 | 0 |
| B | 5 | 1 | 1 |
| A | min(3, 3) = 3 | 0 | 0 |
Critical paths (zero float): A-D-F (3 + 5 + 2 = 10) and A-C-E-F (3 + 2 + 3 + 2 = 10). Two critical paths.
Check: path B-E-F = 4 + 3 + 2 = 9 days, one less than 10, matching B's float of 1.
Floats
- Total float: how long an activity can slip without delaying the project.
- Free float: how long it can slip without delaying any following activity.
PERT: uncertain durations
Each activity has three estimates: optimistic a, most likely m, pessimistic b.
- Expected time tₑ = (a + 4m + b) ÷ 6.
- Variance σ² = ((b − a) ÷ 6)².
Example: a = 2, m = 4, b = 12 → tₑ = (2 + 16 + 12) ÷ 6 = 5 days; σ² = (10 ÷ 6)² ≈ 2.78.
Probability of finishing on time
Add the expected times and the variances along the critical path; assume the total is roughly normal.
A project with expected time 30 days and standard deviation 2 days: P(finish within 33 days) → z = (33 − 30) ÷ 2 = 1.5 → about 93%.
Check: from tables, the area below z = 1.5 is 0.9332.
Crashing
Shortening activities by adding resources at extra cost. Crash the cheapest critical activity per day first, and watch for new critical paths. When two paths are critical (as above), both must be shortened together.
Exams usually ask
- Draw a network, do forward and backward passes, and find the critical path.
- Calculate PERT expected times and a completion probability.
Common mistake
Taking the earliest finish of only one predecessor. An activity starts after all its predecessors finish: use the maximum.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Critical path method
(opens en.wikipedia.org in a new tab)
Wikipedia, Critical path method, CC BY-SA 4.0 · licence
-
Program evaluation and review technique
(opens en.wikipedia.org in a new tab)
Wikipedia, Program evaluation and review technique, CC BY-SA 4.0 · licence
-
Gantt chart
(opens en.wikipedia.org in a new tab)
Wikipedia, Gantt chart, CC BY-SA 4.0 · licence
Watch
-
Best pick CPM (Critical Path Method) in Software Engineering | PERT/CPM Numerical
15 min · ≈ 68 MB · about ₦38
(opens youtube.com in a new tab)
-
Project Scheduling - PERT/CPM | Finding Critical Path
7 min · ≈ 32 MB · about ₦18
(opens youtube.com in a new tab)
-
What is the Critical Path Method (CPM)?
6 min · ≈ 27 MB · about ₦15
(opens youtube.com in a new tab)
-
Lec 52- PERT and CPM
38 min · ≈ 171 MB · about ₦96
(opens youtube.com in a new tab)
We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.