EEE 510 · Power Systems Engineering
Our notes
2 min readWhy per unit
Power systems have many voltage levels. Expressing quantities as a fraction of chosen base values makes impedances of similar equipment fall in narrow ranges, removes the transformer turns ratio from calculations, and simplifies three-phase work.
Per-unit value = actual value ÷ base value (both in the same units).
Choosing bases (three-phase)
Choose a base MVA (S_b, the same everywhere) and a base line voltage (V_b, kV) in one zone; base voltages in other zones follow the transformer ratios. Then:
- Base current I_b = S_b ÷ (√3 × V_b)
- Base impedance Z_b = V_b² ÷ S_b (kV² ÷ MVA gives ohms)
Worked example: a 132 kV line
S_b = 100 MVA, V_b = 132 kV.
- Z_b = 132² ÷ 100 = 17,424 ÷ 100 = 174.24 Ω.
- I_b = 100,000 kVA ÷ (√3 × 132 kV) = 100,000 ÷ 228.63 = 437.4 A.
- Line impedance 20 + j60 Ω: per unit = 20 ÷ 174.24 + j(60 ÷ 174.24) = 0.1148 + j0.3444 pu.
Check: 0.3444 × 174.24 = 60.01 Ω. ✓
Change of base
Equipment data are given on the equipment's own rating. To convert:
Z_new = Z_old × (V_old ÷ V_new)² × (S_new ÷ S_old)
Worked example. A generator rated 50 MVA, 11 kV has X = 0.2 pu. On a 100 MVA, 11 kV base: X = 0.2 × (11 ÷ 11)² × (100 ÷ 50) = 0.4 pu.
Worked example. A motor rated 10 MVA, 6.6 kV, X = 0.15 pu, in a zone whose base is 100 MVA, 6.9 kV: X = 0.15 × (6.6 ÷ 6.9)² × (100 ÷ 10) = 0.15 × 0.9149 × 10 = 1.372 pu. Check: (6.6 ÷ 6.9)² = 0.95652² = 0.91493. ✓
Transformers in per unit
If base voltages on each side are in the ratio of the transformer's rated voltages, the transformer's per-unit impedance is the same on both sides, and the ideal transformer disappears from the circuit. A 100 MVA, 11/132 kV transformer with X = 0.1 pu stays 0.1 pu on a 100 MVA base with bases 11 kV and 132 kV.
Per-unit power
In per unit, S = V × conj(I) for three-phase power, with no √3 factors: one of the big conveniences.
Exams usually ask: compute base current and impedance; convert ohmic values to per unit; change the base of machine data; explain the advantages of the per-unit system.
Common mistake: forgetting the voltage-ratio term when changing base. It matters whenever equipment rated voltage differs from the zone's base voltage.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Best pick Per-unit system
(opens en.wikipedia.org in a new tab)
Wikipedia, Per-unit system, CC BY-SA 4.0 · licence
-
MIT 6.061 Introduction to Electric Power Systems (whole course)
Lecture notes, problem sets and exams as PDFs: per unit, transmission lines, load flow, faults (harder than our notes).
(opens ocw.mit.edu in a new tab)
MIT OpenCourseWare, MIT 6.061 Introduction to Electric Power Systems (whole course), CC BY-NC-SA 4.0 · licence
Watch
-
Per Unit System Made Easy | Power System Analysis for Electrical Engineers
9 min · ≈ 41 MB · about ₦23
(opens youtube.com in a new tab)
-
How to Base Change Per Unit and Percent Impedance Part 1 (Electrical Power PE Exam)
11 min · ≈ 50 MB · about ₦28
(opens youtube.com in a new tab)
-
How to Base Change Per Unit and Percent Impedance Part 2 (Electrical Power PE Exam)
12 min · ≈ 54 MB · about ₦30
(opens youtube.com in a new tab)
-
PS83 Per Unit System
24 min · ≈ 108 MB · about ₦61
(opens youtube.com in a new tab)
-
Lecture -1 Introduction to Power system analysis
1 h · ≈ 270 MB · about ₦152
(opens youtube.com in a new tab)
-
Per Unit Analysis - how does it work? (with examples) || Basics of Power Systems Analysis
28 min · ≈ 126 MB · about ₦71
(opens youtube.com in a new tab)
We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.