Load forecasting

Why forecasts are needed, short-, medium- and long-term forecasts, load factor, demand and diversity factors, forecasting methods (trend, regression, time series, neural networks), and suppressed demand in Nigeria.

Our notes

2 min read

Why forecast

Utilities must plan generation, transmission and distribution years ahead (long-term), schedule maintenance and fuel (medium-term), and commit units and dispatch them hour by hour (short-term). Errors cost money: too little capacity means load shedding; too much means idle investment.

Types

HorizonRangeUse
Very short-termMinutes to an hourReal-time control
Short-termHours to a weekUnit commitment, dispatch
Medium-termWeeks to a yearMaintenance, fuel purchase
Long-term1 to 20 yearsExpansion planning

Load characteristics

  • Demand factor = maximum demand ÷ connected load.
  • Load factor = average load ÷ peak load (over a period).
  • Diversity factor = sum of individual maximum demands ÷ maximum demand of the group (≥ 1).

Worked example. A feeder supplies 1,800 MWh in a day with a peak of 100 MW. Average load = 1,800 ÷ 24 = 75 MW; load factor = 75 ÷ 100 = 0.75. Three feeders have individual peaks of 40, 35 and 45 MW (total 120 MW) but the substation peak is 100 MW: diversity factor = 120 ÷ 100 = 1.2.

Factors affecting load

Time of day, day of week, holidays (Ramadan, Christmas), weather (temperature drives air conditioning), economic activity, population growth, tariffs, and new connections.

Methods

  1. Trend analysis (extrapolating past growth).
  2. Regression: relating load to drivers (GDP, population, temperature).
  3. Time series: moving averages, exponential smoothing, ARIMA.
  4. Artificial neural networks and machine learning: learn complex patterns from data.
  5. End-use models (summing appliance-level demand) and econometric models.

Worked example (linear trend). Peak demand over five years: 100, 108, 115, 124, 133 MW. Let x = 1 to 5.

  • Mean x = 3, mean y = 580 ÷ 5 = 116.
  • Σ(x − 3)(y − 116) = (−2)(−16) + (−1)(−8) + 0 + (1)(8) + (2)(17) = 32 + 8 + 0 + 8 + 34 = 82; Σ(x − 3)² = 10.
  • Slope b = 82 ÷ 10 = 8.2 MW per year; intercept a = 116 − 8.2 × 3 = 91.4.
  • Forecast for year 7: 91.4 + 8.2 × 7 = 148.8 MW.

Check: the line gives 132.4 MW in year 5 against the actual 133 MW. ✓

Suppressed demand in Nigeria

Because supply has long fallen short, the measured grid load is lower than true demand; many homes and businesses run generators. Forecasts based only on past grid load underestimate real demand, so planners add estimates of suppressed and self-generated demand.

Exams usually ask: explain the types and purposes of load forecasting; compute load and diversity factors; fit a trend line and forecast; discuss forecasting methods and their limits.

Common mistake: confusing load factor with diversity factor. Load factor compares average to peak for one load over time; diversity factor compares individual peaks to the combined peak.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All EEE 510 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.