EEE 510 · Power Systems Engineering
Our notes
2 min readWhy forecast
Utilities must plan generation, transmission and distribution years ahead (long-term), schedule maintenance and fuel (medium-term), and commit units and dispatch them hour by hour (short-term). Errors cost money: too little capacity means load shedding; too much means idle investment.
Types
| Horizon | Range | Use |
|---|---|---|
| Very short-term | Minutes to an hour | Real-time control |
| Short-term | Hours to a week | Unit commitment, dispatch |
| Medium-term | Weeks to a year | Maintenance, fuel purchase |
| Long-term | 1 to 20 years | Expansion planning |
Load characteristics
- Demand factor = maximum demand ÷ connected load.
- Load factor = average load ÷ peak load (over a period).
- Diversity factor = sum of individual maximum demands ÷ maximum demand of the group (≥ 1).
Worked example. A feeder supplies 1,800 MWh in a day with a peak of 100 MW. Average load = 1,800 ÷ 24 = 75 MW; load factor = 75 ÷ 100 = 0.75. Three feeders have individual peaks of 40, 35 and 45 MW (total 120 MW) but the substation peak is 100 MW: diversity factor = 120 ÷ 100 = 1.2.
Factors affecting load
Time of day, day of week, holidays (Ramadan, Christmas), weather (temperature drives air conditioning), economic activity, population growth, tariffs, and new connections.
Methods
- Trend analysis (extrapolating past growth).
- Regression: relating load to drivers (GDP, population, temperature).
- Time series: moving averages, exponential smoothing, ARIMA.
- Artificial neural networks and machine learning: learn complex patterns from data.
- End-use models (summing appliance-level demand) and econometric models.
Worked example (linear trend). Peak demand over five years: 100, 108, 115, 124, 133 MW. Let x = 1 to 5.
- Mean x = 3, mean y = 580 ÷ 5 = 116.
- Σ(x − 3)(y − 116) = (−2)(−16) + (−1)(−8) + 0 + (1)(8) + (2)(17) = 32 + 8 + 0 + 8 + 34 = 82; Σ(x − 3)² = 10.
- Slope b = 82 ÷ 10 = 8.2 MW per year; intercept a = 116 − 8.2 × 3 = 91.4.
- Forecast for year 7: 91.4 + 8.2 × 7 = 148.8 MW.
Check: the line gives 132.4 MW in year 5 against the actual 133 MW. ✓
Suppressed demand in Nigeria
Because supply has long fallen short, the measured grid load is lower than true demand; many homes and businesses run generators. Forecasts based only on past grid load underestimate real demand, so planners add estimates of suppressed and self-generated demand.
Exams usually ask: explain the types and purposes of load forecasting; compute load and diversity factors; fit a trend line and forecast; discuss forecasting methods and their limits.
Common mistake: confusing load factor with diversity factor. Load factor compares average to peak for one load over time; diversity factor compares individual peaks to the combined peak.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Nigerian Electricity Regulatory Commission (NERC)
The electricity regulator: the Electricity Act 2023, tariff orders, band A to E supply and quarterly market reports.
(opens nerc.gov.ng in a new tab)
-
Energy forecasting
(opens en.wikipedia.org in a new tab)
Wikipedia, Energy forecasting, CC BY-SA 4.0 · licence
-
Load factor (electrical)
(opens en.wikipedia.org in a new tab)
Wikipedia, Load factor (electrical), CC BY-SA 4.0 · licence
Watch
-
Best pick Introduction To Load Forecasting - Load Forecasting - Power System Planning and Reliability
13 min · ≈ 59 MB · about ₦33
(opens youtube.com in a new tab)
-
Diversity Factor
3 min · ≈ 14 MB · about ₦8
(opens youtube.com in a new tab)
-
Demand Factor
6 min · ≈ 27 MB · about ₦15
(opens youtube.com in a new tab)
-
Importance of high Load factor & Diversity Factor
8 min · ≈ 36 MB · about ₦20
(opens youtube.com in a new tab)
We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.