Overheads: allocation, apportionment and absorption

Sharing factory overheads among cost centres, re-apportioning service departments, and absorbing overheads into products.

Our notes

2 min read

Three steps

  1. Allocation: charge an overhead wholly to the one cost centre that caused it (the canteen manager's salary to the canteen).
  2. Apportionment: share overheads that several cost centres caused, on a fair basis (rent by floor area, insurance of machinery by machine value, power by kilowatt-hours, canteen by number of staff).
  3. Absorption: charge each production centre's overheads to the units passing through it, using an overhead absorption rate (OAR).

Service department re-apportionment

Service departments (stores, maintenance, canteen) do not make products, so their costs are re-apportioned to production departments, by direct method (ignore services to each other), step-down, or repeated distribution / algebra (when they serve each other).

Worked example: apportionment and absorption

Overheads: rent ₦600,000; machine depreciation ₦400,000; canteen ₦180,000.

MachiningAssemblyTotal
Floor area (m²)400200600
Machine value (₦m)314
Staff204060
Rent400,000200,000600,000
Depreciation300,000100,000400,000
Canteen60,000120,000180,000
Total760,000420,0001,180,000
Basis8,000 machine hours14,000 labour hours
OAR₦95 per machine hour₦30 per labour hour

A job using 6 machine hours and 10 labour hours absorbs 6 × 95 + 10 × 30 = 570 + 300 = ₦870 of overhead.

Choosing the absorption base

Machine-hour rate for machine-intensive departments, labour-hour rate for labour-intensive ones. Rates based on output or percentage of prime cost are simpler but less accurate.

Predetermined rates and under/over-absorption

OARs are set at the start of the year from budgeted overheads and budgeted activity. At the year end:

  • Absorbed = OAR × actual activity.
  • Under-absorbed if absorbed < actual overheads (charged as an extra cost to profit or loss); over-absorbed if more (credited).

Worked example

Budgeted overheads ₦760,000 for 8,000 machine hours (OAR ₦95). Actual: overheads ₦790,000; 8,200 hours.

  • Absorbed = 8,200 × 95 = 779,000.
  • Under-absorbed = 790,000 − 779,000 = ₦11,000.

Activity-based costing (a note)

ABC uses many cost pools and cost drivers (number of set-ups, orders, inspections) instead of one hourly rate, giving fairer costs where products differ a lot in complexity.

Exams usually ask

  • Prepare an overhead analysis sheet and compute OARs.
  • Calculate under- or over-absorption and explain its causes.

Common mistake

Calculating absorbed overhead with budgeted hours instead of actual hours.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

Practise

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All ACT 232 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.