Recording labour

Attendance is recorded by clock cards, biometric systems or registers; time spent on each job by job cards or timesheets. The payroll department computes gross pay, deductions (PAYE, pension under the Pension Reform Act 2014, NHF) and net pay.

Methods of pay

Time rate: pay = hours × rate per hour. Simple; no reward for speed; needs supervision.

Piece rate: pay = units × rate per unit. Rewards output; may hurt quality; often with a guaranteed minimum (the national minimum wage applies).

Differential piece rate: higher rate per unit at higher output bands.

Bonus (incentive) schemes

Time allowed (standard time) is set for a job; a worker who finishes faster earns a bonus based on time saved.

  • Halsey: bonus = 50% × time saved × rate.
  • Rowan: bonus = (time taken ÷ time allowed) × time saved × rate.

Worked example

Time allowed 10 hours; time taken 8 hours; rate ₦1,500 an hour.

  • Basic pay = 8 × 1,500 = ₦12,000.
  • Halsey bonus = 50% × 2 × 1,500 = ₦1,500 → total ₦13,500.
  • Rowan bonus = (8 ÷ 10) × 2 × 1,500 = ₦2,400 → total ₦14,400.

Under Rowan the bonus can never make pay double the basic, which protects the firm from loose time standards.

Overtime

Overtime premium is the extra over the basic rate.

  • If overtime is caused by a specific customer's urgent job, the premium is a direct cost of that job.
  • If it is due to general pressure of work, the premium is an overhead.

Example: 45 hours worked, 40 at basic ₦1,200 and 5 at time and a half. Total = 45 × 1,200 + 5 × 600 = 54,000 + 3,000 = ₦57,000; the premium ₦3,000 is usually an overhead.

Idle time

Paid time when no work is done: machine breakdown, power failure, waiting for materials. Normal idle time is built into the hourly cost; abnormal idle time is charged to profit or loss and investigated. Power outages make idle time a big issue for Nigerian factories.

Labour turnover

Labour turnover rate = number of leavers replaced ÷ average number of workers × 100. Costs of high turnover: recruitment, training, lost output, more waste and accidents.

Example: 18 leavers replaced, average workforce 150. Turnover = 18 ÷ 150 = 12%.

Exams usually ask

  • Calculate pay under time rate, piece rate, Halsey and Rowan.
  • Explain the treatment of overtime premium and idle time.

Common mistake

Charging all overtime pay (basic plus premium) as an overhead. The basic part of overtime hours is direct labour if the hours were spent on production.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All ACT 232 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.