SOS 401 · Farm Design, Farm Survey and Land Use Planning

Chain and tape survey

Principles of chain surveying, equipment, ranging lines, offsets, field book entries and errors.

Our notes

2 min read

Principles

  1. Work from the whole to the part: fix a framework of main lines first, then fill in detail. Errors stay small and are found early.
  2. Triangulation: divide the area into well-conditioned triangles (no angle below about 30° or above about 120°), because a triangle's shape is fixed by its three sides.
  3. Check lines (tie lines) test the accuracy of each triangle.

Chain survey suits small, fairly flat, open areas such as most farms.

Equipment

ItemUse
Chain (20 m or 30 m, metric) or tape (steel or fibreglass, 30-50 m)Measuring lengths
Ranging poles (2-3 m, red and white bands)Marking stations and straight lines
Arrows (pins)Marking chain lengths
PegsMarking stations
Offset rodMeasuring short offsets
Optical square or cross-staffSetting out right angles
Field bookRecording measurements
Prismatic compassBearings (compass traverse)

Field procedure

  1. Reconnaissance; choose stations (intervisible, on firm ground) and sketch the framework.
  2. Mark stations with pegs and ranging poles.
  3. Ranging: keep the chain on a straight line between stations by eye with poles (direct ranging) or by two people moving poles in turn when the ends cannot see each other (indirect/reciprocal ranging).
  4. Chain each line, recording distances.
  5. Take offsets: perpendicular (or oblique) distances from the chain line to features (fences, trees, buildings, streams).
  6. Record in the field book: a central column for running distances along the line, offsets to left and right, sketches, station names.

Sloping ground

Measure horizontal distances: stepping (short horizontal lengths held level) or measure along the slope and correct: horizontal = slope length × cos θ.
Example. 50 m along a 10° slope: horizontal = 50 × cos 10° = 50 × 0.9848 = 49.24 m.

Errors

  • Gross errors (mistakes): misreading, wrong counting of chains, wrong booking.
  • Systematic errors: a chain too long or short (standardise against a known length), bad ranging, sag, slope.
  • Random errors: small unavoidable variations.

Correction for a wrong chain: true length = measured length × (actual chain length ÷ nominal length). A "20 m" chain found to be 20.05 m: 300 m measured → 300 × 20.05/20 = 300.75 m.

Obstacles

Use geometric methods (perpendiculars, similar triangles) to chain past ponds, buildings or rivers.

Exams usually ask: principles of chain survey; equipment and their uses; field book booking; correcting for a wrong chain and slope.

Common mistake: measuring along the slope and plotting it as horizontal. On a map every distance must be horizontal.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All SOS 401 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.