SOS 401 · Farm Design, Farm Survey and Land Use Planning
Our notes
2 min readPrinciples
- Work from the whole to the part: fix a framework of main lines first, then fill in detail. Errors stay small and are found early.
- Triangulation: divide the area into well-conditioned triangles (no angle below about 30° or above about 120°), because a triangle's shape is fixed by its three sides.
- Check lines (tie lines) test the accuracy of each triangle.
Chain survey suits small, fairly flat, open areas such as most farms.
Equipment
| Item | Use |
|---|---|
| Chain (20 m or 30 m, metric) or tape (steel or fibreglass, 30-50 m) | Measuring lengths |
| Ranging poles (2-3 m, red and white bands) | Marking stations and straight lines |
| Arrows (pins) | Marking chain lengths |
| Pegs | Marking stations |
| Offset rod | Measuring short offsets |
| Optical square or cross-staff | Setting out right angles |
| Field book | Recording measurements |
| Prismatic compass | Bearings (compass traverse) |
Field procedure
- Reconnaissance; choose stations (intervisible, on firm ground) and sketch the framework.
- Mark stations with pegs and ranging poles.
- Ranging: keep the chain on a straight line between stations by eye with poles (direct ranging) or by two people moving poles in turn when the ends cannot see each other (indirect/reciprocal ranging).
- Chain each line, recording distances.
- Take offsets: perpendicular (or oblique) distances from the chain line to features (fences, trees, buildings, streams).
- Record in the field book: a central column for running distances along the line, offsets to left and right, sketches, station names.
Sloping ground
Measure horizontal distances: stepping (short horizontal lengths held level) or measure along the slope and correct: horizontal = slope length × cos θ.
Example. 50 m along a 10° slope: horizontal = 50 × cos 10° = 50 × 0.9848 = 49.24 m.
Errors
- Gross errors (mistakes): misreading, wrong counting of chains, wrong booking.
- Systematic errors: a chain too long or short (standardise against a known length), bad ranging, sag, slope.
- Random errors: small unavoidable variations.
Correction for a wrong chain: true length = measured length × (actual chain length ÷ nominal length). A "20 m" chain found to be 20.05 m: 300 m measured → 300 × 20.05/20 = 300.75 m.
Obstacles
Use geometric methods (perpendiculars, similar triangles) to chain past ponds, buildings or rivers.
Exams usually ask: principles of chain survey; equipment and their uses; field book booking; correcting for a wrong chain and slope.
Common mistake: measuring along the slope and plotting it as horizontal. On a map every distance must be horizontal.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Surveying
(opens en.wikipedia.org in a new tab)
Wikipedia, Surveying, CC BY-SA 4.0 · licence
-
Chain (unit)
(opens en.wikipedia.org in a new tab)
Wikipedia, Chain (unit), CC BY-SA 4.0 · licence
-
Tape measure
(opens en.wikipedia.org in a new tab)
Wikipedia, Tape measure, CC BY-SA 4.0 · licence
Watch
-
Best pick Chain surveying: Offsetting
2 min · ≈ 9 MB · about ₦5
(opens youtube.com in a new tab)
-
OBSTACLES IN CHAIN SURVEYING
7 min · ≈ 32 MB · about ₦18
(opens youtube.com in a new tab)
-
Offsets in survey / Perpendicular and oblique offsets / Field book / Survey - unit 2 - part 7
23 min · ≈ 104 MB · about ₦58
(opens youtube.com in a new tab)
-
Tape & Offset Surveys | Chain Surveys | Plan/Map Scale
35 min · ≈ 158 MB · about ₦89
(opens youtube.com in a new tab)
We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.