What surveying is

Surveying is measuring the positions, distances, heights and angles of features on the ground in order to draw maps and plans. Practical geography introduces the simple methods; Surveying and Geoinformatics departments go much further.

Two principles

  1. Work from the whole to the part: fix a framework of control points first, then fill in detail. Errors stay contained.
  2. Fix each new point by at least two measurements from known points, so mistakes can be checked.

Chain survey

For small, fairly flat areas.

  • Equipment: chain or tape (20 m or 30 m), ranging poles, arrows (pins), offset rod, field book.
  • Lay out a framework of triangles (well-conditioned: no angle smaller than about 30°), because a triangle's shape is fixed by its three sides.
  • Measure each line; from each line, measure offsets at right angles to features such as buildings or fences.
  • Record measurements in the field book from bottom to top, with the chain line drawn up the middle of the page.

Compass (traverse) survey

For long, narrow areas such as roads or rivers.

  • Measure the bearing and length of each leg in turn.
  • In a closed traverse you return to the start; the gap on the plot is the closing error, which is shared out along the legs (Bowditch's method is the standard way).
  • Prismatic compasses can be upset by iron objects and power lines (local attraction): check with back bearings, which should differ from forward bearings by exactly 180°.

Levelling

Finds height differences between points.

  • Equipment: a level (an instrument with a horizontal line of sight) and a graduated staff.
  • Rise and fall method: read the staff at a known point (back sight) and at the next point (fore sight). If the fore sight is smaller, the ground has risen by the difference.

Example: Back sight at a bench mark (height 25.00 m) = 1.85 m. Fore sight at point P = 0.95 m. Rise = 1.85 − 0.95 = 0.90 m. Height of P = 25.90 m.
Check by height of instrument: 25.00 + 1.85 = 26.85 m; 26.85 − 0.95 = 25.90 m. ✓

Plane table survey

A drawing board on a tripod: you draw the map in the field by sighting features with an alidade and drawing rays. Good for teaching and quick detail.

Modern tools

Total stations measure angles and distances electronically; GNSS (GPS) receivers fix positions directly; drones capture photos for mapping. The principles above still apply.

Exams usually ask

  • State the principles of surveying.
  • Describe a chain or compass survey and how errors are checked.
  • Work out heights by rise and fall.

Common mistake

Using badly shaped (very thin) triangles in a chain survey. A small error in a side then moves a point a long way.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All GEM 102.1 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.