Project risk, sensitivity and capital rationing

Handling uncertainty with sensitivity and scenario analysis, risk-adjusted discount rates and certainty equivalents, and choosing projects when capital is limited.

Our notes

2 min read

Why risk analysis

Cash flow forecasts are uncertain (fuel prices, exchange rate, demand). Before accepting a project, ask how wrong a forecast can be before NPV turns negative.

Sensitivity analysis

Change one variable at a time and see the effect on NPV, or find the percentage change that makes NPV zero:
sensitivity = NPV / PV of the cash flows affected by that variable.
Worked example (the project from investment appraisal: NPV ₦697,285, PV of inflows ₦10,697,285).

  • Inflows: 697,285 / 10,697,285 = 6.5%. If every inflow falls by more than 6.5%, NPV turns negative.
  • Initial cost: 697,285 / 10,000,000 = 7.0% overrun allowed.

The smaller the percentage, the more critical the variable; management should check those forecasts hardest.
Weakness: variables often change together.

Scenario analysis

Change several variables together: worst case, most likely, best case. Combine with probabilities for an expected NPV.

Simulation (Monte Carlo)

Many random trials of all variables give a distribution of NPVs and the probability of a loss. Needs software.

Adjusting for risk directly

  • Risk-adjusted discount rate: add a premium for riskier projects (or use a project β in CAPM).
  • Certainty equivalent: convert each uncertain cash flow to the certain amount the firm would accept instead, then discount at the risk-free rate.
  • Payback limit: a short payback cut-off as a rough guard against risk (common in unstable economies).

Capital rationing

When funds are limited, not every positive-NPV project can be taken.

  • Hard rationing: lenders and markets will not supply more.
  • Soft rationing: management sets a budget limit.

Divisible projects: rank by profitability index (NPV per naira invested).
Indivisible projects: test the combinations that fit the budget and pick the highest total NPV.
Worked example. Budget ₦20m.

ProjectCostNPVPI (PV/cost)
A10m3.0m1.30
B8m2.0m1.25
C6m2.4m1.40

Divisible: C (6m), then A (10m): 16m used, 4m left for half of B (NPV 1.0m). Total NPV ₦6.4m.
Indivisible: A + B = 18m, NPV 5.0m; A + C = 16m, NPV 5.4m; B + C = 14m, NPV 4.4m. Choose A + C.

Exams usually ask: sensitivity of NPV to each variable; expected NPV with probabilities; risk-adjusted rates versus certainty equivalents; single-period capital rationing with divisible and indivisible projects.

Common mistake: ranking by NPV alone under capital rationing. With limited money, rank divisible projects by NPV per naira (PI).

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All FIN 333 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.