Contract management

Choosing contract types, risk allocation, administering contracts, variations and claims, performance monitoring and close-out.

Our notes

3 min read

What contract management is

Managing a contract from planning through award and delivery to close-out, so that both parties meet their obligations and the project gets the agreed scope, quality, time and cost. (The legal basics of contract are in ENG 501.)

Choosing the contract type

TypePrice basisRisk to contractorUse
Lump sum (fixed price)one price for defined workhighwell-defined scope
Re-measurement (bill of quantities)unit rates × measured quantitiesmediumcivil works where quantities vary
Cost reimbursable (cost plus fee)actual cost + feelow (client carries risk)urgent or poorly defined work
Target costcost reimbursable with shared savings or overrunssharedencourages cooperation
EPC / turnkeylump sum for design, procurement and constructionvery highprocess plants, oil and gas
Service and maintenance contractsrates per call-out, per month, or performance-basedvariesoperations
Framework (call-off) agreementsagreed rates for repeated worklow-mediumroutine maintenance, small projects

Rule: give each risk to the party best able to manage it; transferring a risk the contractor cannot control raises prices or causes disputes.

Before award

  • Clear scope of work and specifications.
  • Choose a standard form (FIDIC, NEC or the client's own) and adapt it carefully.
  • Pre-qualify bidders (capacity, experience, finance, HSE record, COREN-registered firm).
  • Evaluate bids technically and commercially; check for very low "suicide" bids.
  • Negotiate and sign; obtain performance bonds, advance payment guarantees and insurance.

During the contract

  1. Kick-off meeting: roles, communication channels, procedures, programme.
  2. Monitor performance: progress against the programme, quality inspections and tests, HSE compliance.
  3. Payments: measure work, certify interim payments, retain a percentage (retention, often 5-10%) until completion and the defects period.
  4. Variations (changes): a written instruction from the authorised person; agree the price and time effect (using contract rates where possible) before the work if practicable.
  5. Claims: for extra time or money from events the contract places on the other party (late drawings, site access delays, unforeseen ground conditions). Contracts set notice periods: a contractor who fails to give notice may lose the right to claim.
  6. Records: site diaries, minutes, photographs, correspondence, test certificates: the basis of resolving any dispute.
  7. Disputes: negotiation, adjudication or dispute boards, then arbitration (ENG 501).

Example: retention

Interim certificate for work valued at ₦20 million, retention 10%, previous payments ₦12 million (net of retention).

  • Retention held: ₦2 million.
  • Amount due now = 20 − 2 − 12 = ₦6 million.

Half the retention is often released at completion and the rest at the end of the defects liability period.

Close-out

Completion certificate, punch list cleared, as-built drawings and manuals handed over, final account agreed, retention released, bonds returned, lessons learnt recorded, and supplier and contractor performance evaluated for future work.

Good practice

Clear contracts, fair risk sharing, prompt payment (late payment harms small Nigerian contractors and leads to abandoned work), professional and documented communication, and integrity (no "returns" or kickbacks: corruption raises costs and lowers quality).

Exams usually ask

  • Compare types of contract and their risk allocation.
  • Describe the duties of a contract manager during a contract.
  • Explain variations, claims and retention; calculate an interim payment.

Common mistake

Allowing work to change on verbal instructions. Undocumented variations are a main source of claims and disputes; instruct in writing.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All ENG 502 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.