ENG 502 · Engineering Management
Our notes
3 min readWhat contract management is
Managing a contract from planning through award and delivery to close-out, so that both parties meet their obligations and the project gets the agreed scope, quality, time and cost. (The legal basics of contract are in ENG 501.)
Choosing the contract type
| Type | Price basis | Risk to contractor | Use |
|---|---|---|---|
| Lump sum (fixed price) | one price for defined work | high | well-defined scope |
| Re-measurement (bill of quantities) | unit rates × measured quantities | medium | civil works where quantities vary |
| Cost reimbursable (cost plus fee) | actual cost + fee | low (client carries risk) | urgent or poorly defined work |
| Target cost | cost reimbursable with shared savings or overruns | shared | encourages cooperation |
| EPC / turnkey | lump sum for design, procurement and construction | very high | process plants, oil and gas |
| Service and maintenance contracts | rates per call-out, per month, or performance-based | varies | operations |
| Framework (call-off) agreements | agreed rates for repeated work | low-medium | routine maintenance, small projects |
Rule: give each risk to the party best able to manage it; transferring a risk the contractor cannot control raises prices or causes disputes.
Before award
- Clear scope of work and specifications.
- Choose a standard form (FIDIC, NEC or the client's own) and adapt it carefully.
- Pre-qualify bidders (capacity, experience, finance, HSE record, COREN-registered firm).
- Evaluate bids technically and commercially; check for very low "suicide" bids.
- Negotiate and sign; obtain performance bonds, advance payment guarantees and insurance.
During the contract
- Kick-off meeting: roles, communication channels, procedures, programme.
- Monitor performance: progress against the programme, quality inspections and tests, HSE compliance.
- Payments: measure work, certify interim payments, retain a percentage (retention, often 5-10%) until completion and the defects period.
- Variations (changes): a written instruction from the authorised person; agree the price and time effect (using contract rates where possible) before the work if practicable.
- Claims: for extra time or money from events the contract places on the other party (late drawings, site access delays, unforeseen ground conditions). Contracts set notice periods: a contractor who fails to give notice may lose the right to claim.
- Records: site diaries, minutes, photographs, correspondence, test certificates: the basis of resolving any dispute.
- Disputes: negotiation, adjudication or dispute boards, then arbitration (ENG 501).
Example: retention
Interim certificate for work valued at ₦20 million, retention 10%, previous payments ₦12 million (net of retention).
- Retention held: ₦2 million.
- Amount due now = 20 − 2 − 12 = ₦6 million.
Half the retention is often released at completion and the rest at the end of the defects liability period.
Close-out
Completion certificate, punch list cleared, as-built drawings and manuals handed over, final account agreed, retention released, bonds returned, lessons learnt recorded, and supplier and contractor performance evaluated for future work.
Good practice
Clear contracts, fair risk sharing, prompt payment (late payment harms small Nigerian contractors and leads to abandoned work), professional and documented communication, and integrity (no "returns" or kickbacks: corruption raises costs and lowers quality).
Exams usually ask
- Compare types of contract and their risk allocation.
- Describe the duties of a contract manager during a contract.
- Explain variations, claims and retention; calculate an interim payment.
Common mistake
Allowing work to change on verbal instructions. Undocumented variations are a main source of claims and disputes; instruct in writing.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Best pick Business Law I Essentials, 7.1 Agreement, Consideration, and Promissory Estoppel
(opens openstax.org in a new tab)
OpenStax, Business Law I Essentials, 7.1 Agreement, Consideration, and Promissory Estoppel, CC BY-NC-SA 4.0 · licence
-
Contract management
(opens en.wikipedia.org in a new tab)
Wikipedia, Contract management, CC BY-SA 4.0 · licence
-
International Federation of Consulting Engineers
(opens en.wikipedia.org in a new tab)
Wikipedia, International Federation of Consulting Engineers, CC BY-SA 4.0 · licence
-
OpenStax, Principles of Management (whole free textbook)
The whole book, free to read online or download as a PDF (the PDF is large: Wi-Fi).
(opens openstax.org in a new tab)
OpenStax, OpenStax, Principles of Management (whole free textbook), CC BY-NC-SA 4.0 · licence
Watch
-
Types of Construction Contracts: An Overview of 6 Common Structures!
21 min · ≈ 95 MB · about ₦53
(opens youtube.com in a new tab)
-
Introduction to FIDIC: Understanding the Basic Types of International Construction Contracts
23 min · ≈ 104 MB · about ₦58
(opens youtube.com in a new tab)
-
Construction Contract Administration Basics (and Tips for Success) (Part 1)
20 min · ≈ 90 MB · about ₦51
(opens youtube.com in a new tab)
-
📚 STANDARD FORMS OF CONSTRUCTION CONTRACT | JCT, NEC & FIDIC EXPLAINED
8 min · ≈ 36 MB · about ₦20
(opens youtube.com in a new tab)
We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.