ENG 402 · Engineering Economics

Comparing alternatives: present worth and annual worth

Net present worth, comparing mutually exclusive alternatives, equal and unequal lives, annual worth, and capitalised cost.

Our notes

2 min read

Present worth (PW, or net present value NPV)

Discount every cash flow to time 0 at the MARR and add them. Accept a single project if PW ≥ 0; among mutually exclusive projects choose the highest PW (or the lowest PW of costs when only costs differ).
Worked example. Invest ₦1,000,000, receive ₦300,000 a year for 5 years, MARR 10%: PW = −1,000,000 + 300,000 × 3.7908 = +₦137,240: accept.

Comparing two machines with equal lives (costs only)

MARR 10%, life 5 years. (P/A, 10%, 5) = 3.7908; (P/F, 10%, 5) = 0.62092.

Machine AMachine B
First cost1,000,0001,500,000
Annual operating cost200,000120,000
Salvage at year 5100,000200,000

PW of costs A = 1,000,000 + 200,000 × 3.7908 − 100,000 × 0.62092 = 1,000,000 + 758,160 − 62,092 = ₦1,696,068.
PW of costs B = 1,500,000 + 120,000 × 3.7908 − 200,000 × 0.62092 = 1,500,000 + 454,896 − 124,184 = ₦1,830,712.
Choose A (lower present cost), by about ₦135,000.

Unequal lives

Present worth must compare the same service period: use the least common multiple of lives (repeat each machine), or a fixed study period. Easier: use annual worth.

Annual worth (AW) or equivalent uniform annual cost (EUAC)

Convert all cash flows to an equal yearly amount: AW = PW × (A/P, i, n). With repeatable alternatives, AW over one life equals AW over many lives, so unequal lives are handled directly.

  • Capital recovery cost of an asset: CR = (P − S)(A/P, i, n) + S × i.

Worked example (unequal lives). MARR 10%, no salvage. Pump X costs ₦300,000, lasts 3 years, costs ₦40,000 a year to run; pump Y costs ₦500,000, lasts 6 years, costs ₦30,000 a year.
(A/P, 10%, 3) = 0.1331/0.331 = 0.40211; (A/P, 10%, 6) = 0.177156/0.771561 = 0.22961.
EUAC X = 300,000 × 0.40211 + 40,000 = ₦160,634; EUAC Y = 500,000 × 0.22961 + 30,000 = ₦144,804. Choose Y, although it costs more at first.

Capitalised cost

For very long-lived public works (dams, bridges, roads), the present worth of costs going on forever: CC = first cost + (annual cost)/i (+ periodic costs turned into an annual amount first).
Worked example. A bridge costs ₦800 million, ₦12 million a year to maintain, and needs ₦50 million of resurfacing every 10 years; i = 8%. Resurfacing as an annual amount: 50 × (A/F, 8%, 10) = 50 × 0.08/(2.158925 − 1) = 50 × 0.06903 = ₦3.45 million. CC = 800 + (12 + 3.45)/0.08 = 800 + 193.1 = ₦993 million.

Future worth

Moving everything to the end instead (FW = PW × (F/P)) gives the same decision; useful when the question is "what will we have at the end?".

Exams usually ask: compute PW and AW of a project; compare equal-life alternatives by PW; compare unequal-life alternatives by AW; capital recovery; capitalised cost; explain why lives must match for PW.

Common mistake: comparing the PW of a 3-year machine with that of a 6-year machine directly. That compares 3 years of service with 6; use AW or a common study period.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All ENG 402 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.