CSC 486 · Systems Analysis And Design

Testing, conversion and implementation

Levels and types of testing, test plans and data, installing the system, user training, data conversion, and the changeover methods (direct, parallel, phased, pilot).

Our notes

2 min read

Testing levels

  1. Unit testing: each module alone.
  2. Integration testing: modules together (do they pass data correctly?).
  3. System testing: the whole system against the requirements, including performance, security, load ("can it take 10,000 students registering on the last day?").
  4. User acceptance testing (UAT): users test with real tasks and sign off. Alpha testing at the developer's site; beta at users' sites.

Testing approaches

  • Black-box: test inputs and outputs against the specification without looking at the code.
  • White-box (glass-box): test paths and branches inside the code.
  • Regression testing: retest after changes to check nothing else broke.
  • Test data: normal, boundary (extreme) and erroneous (invalid) data, with expected results written before running.
TestInputExpected
Normal18 unitssaved
Boundary24 unitssaved
Boundary25 unitsrejected: "maximum is 24"
Erroneous"abc" unitsrejected: "enter a number"

Implementation activities

  • Site preparation and installation of hardware, network and software.
  • User training: manuals, hands-on sessions, train-the-trainer, help desk, short videos.
  • Data conversion: move existing records into the new system (typing, scanning, import scripts); clean data first; verify totals after conversion.
  • Documentation handed over.

Changeover (conversion) methods

MethodHowProsCons
Direct (plunge)old system stops, new starts on a set datecheapest, quickhighest risk: if the new system fails there is no fallback
Parallel runningold and new run together until the new is trusted; results comparedsafest; results can be checkedmost costly; double work for staff
Phasednew system introduced in stages (module by module)lower risk, staff learn graduallyslow; old and new must work together
Pilotwhole system tried in one part first (one faculty), then everywhereproblems found on a small scalethat part bears the risk; takes time

Parallel runs are usual for payroll and accounts, where errors are costly: the outputs of both systems are compared for, say, two pay cycles.

Choosing a method

Consider risk, cost, staff workload, how different the systems are, and whether the old system can still run.

Managing change

People resist new systems (fear of job loss, new skills, loss of control). Reduce it by involving users early, communicating benefits, training well and giving support after go-live.

Exams usually ask: levels of testing; black-box vs white-box; design test data for a field; implementation activities; compare the four changeover methods with examples; why parallel runs are used.

Common mistake: calling parallel running "phased". Parallel means both whole systems run at once; phased means the new one comes in piece by piece.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All CSC 486 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.