Feasibility study and cost-benefit analysis

Technical, economic, operational, schedule and legal feasibility, tangible and intangible costs and benefits, payback period and net present value with worked examples.

Our notes

2 min read

What it is

A feasibility study decides whether a proposed system is worth building. It is done early, before big money is spent, and ends with a recommendation to management.

Types of feasibility (TELOS)

  • Technical: is the hardware, software and expertise available? Can it handle the volume?
  • Economic: do the benefits outweigh the costs (cost-benefit analysis)?
  • Legal: does it obey laws, licences and contracts (the Nigeria Data Protection Act 2023 for personal data)?
  • Operational: will users accept and use it? Does it fit the organisation's way of working? Will staff resist?
  • Schedule: can it be done in the time available?

Costs and benefits

Tangible (measurable in money)Intangible (hard to measure)
Costshardware, software licences, development, training, data conversion, maintenance, powerstaff disruption, lower morale during change
Benefitsfewer staff hours, less paper, fewer errors, faster fees collectionbetter decisions, better service, image, staff satisfaction

Costs are also one-off (development) or recurring (operating).

Payback period

Time until cumulative savings equal the investment.
Worked example. A system costs ₦6,000,000 to build and saves ₦2,500,000 a year in running costs. Payback = 6,000,000 ÷ 2,500,000 = 2.4 years (about 2 years 5 months).

Return on investment

ROI = (total benefits − total costs) ÷ total costs × 100%. Over 5 years, savings 12,500,000 against cost 6,000,000: ROI = 6,500,000 ÷ 6,000,000 × 100 = 108%.

Net present value (NPV)

Money received later is worth less than money now, so future benefits are discounted: present value = amount ÷ (1 + r)ⁿ.
Worked example. Cost ₦6,000,000 now; savings ₦2,500,000 at the end of each of 3 years; discount rate 10%.
PV year 1 = 2,500,000/1.1 = 2,272,727. Year 2 = 2,500,000/1.21 = 2,066,116. Year 3 = 2,500,000/1.331 = 1,878,287. Total PV = 6,217,130.
NPV = 6,217,130 − 6,000,000 = +₦217,130. Positive NPV → worthwhile at 10% (at a higher rate, say Nigeria's high interest rates, it might turn negative: test with the real rate).

Break-even point

The point in time where cumulative benefits equal cumulative costs, often shown on a graph.

The feasibility report

Contents: introduction and terms of reference, description of the current system and its problems, proposed alternatives (e.g. do nothing, improve the manual system, buy a package, build a custom system), feasibility of each, cost-benefit analysis, recommendation, and appendices.

Evaluating alternatives

Use a weighted scoring table: list criteria (cost, ease of use, vendor support, speed of delivery), give each a weight, score each option, multiply and add; the highest total wins (but judgement still matters).

Exams usually ask: define a feasibility study; explain the types; tangible vs intangible costs and benefits; payback, ROI and NPV calculations; contents of the feasibility report.

Common mistake: in NPV, forgetting to discount each year by its own power (year 2 divides by 1.1², not 1.1 × 2).

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All CSC 486 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.