AGX 501 · Programme Development and Planning in Agric Extension

Long- and short-range programmes, plans of work and calendars of work

Planning horizons, the contents of a plan of work, building a calendar of work, and an example.

Our notes

2 min read

Long-range and short-range programmes

  • Long-range programme: covers several years (often 3-5); states the broad situation, major problems, long-term goals and general strategies (for example, reducing post-harvest losses in cassava and fish in an LGA over five years). It gives direction and continuity.
  • Short-range programme: covers one year or one season; selects specific problems and objectives from the long-range programme for immediate action. It is translated into a plan of work.

The long-range programme is the "map"; the short-range plan is "the next part of the journey".

The plan of work

The plan of work is the detailed working document for a period (usually a year). Contents:

  1. Problems and objectives (from the programme) to be tackled.
  2. Target audiences and numbers.
  3. Activities and teaching methods (demonstrations, meetings, visits, radio programmes, training).
  4. Learning experiences and subject matter.
  5. Responsibilities: who does what (agent, specialist, local leader, partner agency).
  6. Location of each activity.
  7. Timing.
  8. Resources and budget: materials, inputs, transport, funds.
  9. Cooperating agencies.
  10. Indicators and methods of evaluation.

Qualities: written, realistic, specific, flexible, agreed with local leaders, linked to objectives.

The calendar of work

The calendar of work arranges the plan's activities by date, usually month by month (or week by week), so that each activity happens at the right time in the farming season and staff and resources are not overloaded. It is often drawn as a table or Gantt chart (activities as rows, time as columns with bars).
Rules:

  • Follow the seasonal farming calendar (rains, planting, weeding, harvesting, market periods).
  • Avoid clashes with festivals, market days and peak labour periods.
  • Leave time for preparation and follow-up.
  • Spread workload evenly.

Example: part of a calendar of work (cassava programme, southern Nigeria)

MonthActivityWhoTarget
JanuaryPlan with farmer groups; select demonstration sitesagent, group leaders6 villages
FebruaryTraining of lead farmers on improved varietiesspecialist30 lead farmers
March-AprilStem distribution; method demonstrations on planting and spacingagent, lead farmers300 farmers
May-JuneFollow-up visits; weed control demonstrationsagent300 farmers
JulyRadio programme series on pest and disease controlagent, radio stationwhole LGA
OctoberMid-season review with groupsagent, groups6 groups
December-JanuaryField day at harvest; yield measurementagent, specialist, groups500 visitors
JanuaryEvaluation and re-planning meetingallall groups

Monthly and weekly plans

Agents break the calendar down into monthly and weekly work plans and keep diaries and reports recording what was done, which feed into monitoring.

Exams usually ask

  • Distinguish long-range from short-range programmes.
  • Explain the contents of a plan of work.
  • Prepare a calendar of work for a given extension programme.

Common mistake

Preparing a calendar of work that ignores the farming season (planting demonstrations scheduled in the dry season). Timing is the whole point of the calendar.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All AGX 501 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.