- Operations needed and the time available (the planting window).
- Size (capacity) to finish the work on time: area ÷ (effective capacity × hours available).
- Power match between tractor and implement.
- Availability of spare parts and service (a common dealer brand is safer).
- Cost: price, running costs, resale value.
- Operator skill, safety and soil conditions.
Maintenance and storage
Daily checks, lubrication, timely servicing (see the engine topic); clean implements after use, grease bearings, paint or oil steel parts; store under a roof off the ground; release tension on belts; record all work done.
Costs
Fixed (ownership) costs, paid whether or not the machine works: depreciation, interest on the money tied up, housing, insurance and tax.
Variable (operating) costs: fuel, lubricants, repairs and maintenance, operator's wages.
- Straight-line depreciation per year = (purchase price − salvage value) ÷ life in years.
- Interest per year = (purchase price + salvage value) ÷ 2 × interest rate.
Worked example: cost per hectare
A tractor with plough costs ₦30,000,000 (practice figure), salvage value 10% (₦3,000,000), life 10 years, interest 15%, housing and insurance 2% of price a year, used 600 hours a year.
- Depreciation = (30,000,000 − 3,000,000) ÷ 10 = ₦2,700,000.
- Interest = (30,000,000 + 3,000,000) ÷ 2 × 0.15 = ₦2,475,000.
- Housing and insurance = 0.02 × 30,000,000 = ₦600,000.
- Fixed cost per year = ₦5,775,000; per hour = 5,775,000 ÷ 600 = ₦9,625.
- Variable per hour: fuel 8 L × ₦1,000 = ₦8,000; lubricants 15% of fuel = ₦1,200; repairs ₦3,000; operator ₦1,500; total ₦13,700.
- Total per hour = 9,625 + 13,700 = ₦23,325.
- At an effective capacity of 0.4 ha/h: 23,325 ÷ 0.4 = ₦58,312 per hectare.
Check: fixed + variable per hectare = 24,062.5 + 34,250 = 58,312.5. ✓
Owning or hiring
If the tractor works only 200 hours a year, the fixed cost per hour becomes 5,775,000 ÷ 200 = ₦28,875, and the total is 28,875 + 13,700 = ₦42,575 per hour (₦106,438 per hectare). If hire costs less than that, hiring (or sharing in a cooperative) is cheaper. Fixed costs fall per hour as use rises: high use justifies ownership.
Records
Keep for each machine: purchase details, hours worked (hour meter), fuel used, services and repairs with dates and costs, breakdowns, and the operator. Records show the true cost, when a machine should be replaced, and support loans and hire pricing.
Exams usually ask: state factors in selecting farm machinery; distinguish fixed and variable costs; calculate depreciation, interest and cost per hour or hectare; explain the importance of machinery records.
Common mistake: leaving out fixed costs when pricing tractor hire. A machine that "only uses fuel" is losing value and tying up money every year.
Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.
Read
-
Best pick Depreciation
(opens en.wikipedia.org in a new tab)
Wikipedia, Depreciation, CC BY-SA 4.0 · licence
-
NOUN CRP 312: Farm Power and Agricultural Mechanization
NOUN course book (PDF, about 3.1 MB). Ten modules: farm power sources, the engine, tractor transmission, hydraulics and three-point linkage, tillage and planting, livestock and irrigation equipment, combines, crop drying and machinery cost estimation.
(opens nou.edu.ng in a new tab)
-
Fixed cost
(opens en.wikipedia.org in a new tab)
Wikipedia, Fixed cost, CC BY-SA 4.0 · licence
-
Variable cost
(opens en.wikipedia.org in a new tab)
Wikipedia, Variable cost, CC BY-SA 4.0 · licence
We link to free material and never copy it. Every link was opened by our team before it went up.