ACT 232 · Introduction to Cost and Management Accounting

Job, batch and contract costing

Costing one-off customer orders, batches of identical items and long construction contracts.

Our notes

2 min read

Job costing

Used when each order is different and made to a customer's specification: printing, furniture making, vehicle repairs, tailoring. Each job has a job cost card collecting direct materials, direct labour, direct expenses and absorbed overheads.

Worked example: job cost and price

Job 47, a set of office desks: direct materials ₦180,000; direct labour 40 hours at ₦1,500; production overhead ₦800 per labour hour; administration overhead 10% of production cost; profit mark-up 25% on total cost.

  • Direct labour = 40 × 1,500 = 60,000. Prime cost = 240,000.
  • Production overhead = 40 × 800 = 32,000. Production cost = 272,000.
  • Administration = 10% × 272,000 = 27,200. Total cost = 299,200.
  • Price = 299,200 × 1.25 = ₦374,000.

If the customer asks for a 20% margin on the price instead: price = 299,200 ÷ 0.8 = ₦374,000. A 25% mark-up equals a 20% margin.

Batch costing

A batch of identical units is treated as one job, and the batch cost is divided by the number of good units: shoes, bakery orders, medicines. Set-up costs are spread over the batch, so bigger batches cut the cost per unit (an EOQ-like trade-off with holding cost).

Example: batch cost ₦450,000 for 1,500 loaves, 3% spoiled. Good units = 1,455; cost per good loaf = 450,000 ÷ 1,455 = ₦309.28.

Contract costing

For long, large jobs (roads, buildings, bridges), often lasting more than one year and done mainly at the site. Costs are charged to a contract account: materials delivered to site, site labour, plant (depreciation or hire), subcontractors, site overheads, a share of head-office costs.

Customers pay in stages based on an architect's or engineer's certificate of work done; part is held back as retention until defects are fixed.

Recognising profit on an unfinished contract

Under IFRS 15, revenue and profit are recognised as work progresses, if the outcome can be estimated reliably. A simple method:

Profit recognised = estimated total profit × (cost to date ÷ estimated total cost)

If a loss is expected, it is recognised in full at once.

Worked example

Contract price ₦50 m; cost to date ₦18 m; estimated further cost ₦22 m.

  • Estimated total cost = 40 m; estimated total profit = 10 m.
  • Stage of completion = 18 ÷ 40 = 45%.
  • Profit to recognise = 45% × 10 m = ₦4.5 m.
  • Revenue to recognise = 45% × 50 m = ₦22.5 m.

Exams usually ask

  • Prepare a job cost card and price a job.
  • Prepare a contract account and calculate the profit to take.

Common mistake

Taking profit on a contract that is expected to make a loss overall. The whole expected loss is recognised now.

Written by the UniHive team in our own words. Spotted a mistake? Tell us on WhatsApp.

Read

Watch

Practise

We link to free material and never copy it. Every link was opened by our team before it went up; video data is a rough guide at 360p.

All ACT 232 topics

Report

Sign in to report this. It is free.

Is this your work (a lecturer, author or publisher)? Ask us to take it down.